IV locating the Boiler
1) Clearances:
•
Observe the minimum clearances shown below. Except as noted, these clearances apply to all combustible con
-
struction, as well as noncombustible walls, ceilings and doors. Also see Figure 4.0.
Front – 24”
Left Side – 6”
Right Side – 6”
Rear – 6”
Top – 6”
Single Wall Chimney Connector (to combustible construction) - 18”
•
A 24” service clearance from the jacket is recommended from the top of the boiler. This clearance may be
reduced to that shown above; however, servicing the boiler will become increasingly difficult as this clearance
is reduced.
2) If listed Type L vent is used, follow vent pipe manufacturer recommendations for minimum clearances.
3) Do not install this boiler directly on a combustible surface. Where it is desired to install the TWZ over a non-carpeted
combustible surface, install the boiler on the base shown in Figure 4.1.
4) Do not install this boiler in a location where gasoline or other flammable vapors or liquids will be stored or used. Do not
install this boiler in an area where large amounts of airborne dust will be present, such as a workshop.
WARNING
FAILURE TO OBSERVE THE FOLLOWING LOCATION REQUIREMENTS COULD RESULT
IN PROPERTY DAMAGE, A FIRE, EXPLOSION OR CARBON MONOXIDE (CO) HAZARD.
FIGurE 4.0: clEarancEs
`
Содержание TWZ065
Страница 2: ......
Страница 8: ...6 FIGURE 4 1 installation over a combustible floor ...
Страница 25: ...23 FIGURE 10 0 CONNECTIONS DIAGRAM BOILERS LESS TANKLESS HEATER COLD START CONTROL ...
Страница 26: ...24 FIGURE 10 1 CONNECTIONS DIAGRAM BOILERS WITH TANKLESS HEATER WARM START CONTROL ...
Страница 27: ...25 FIGURE 10 2 CONNECTIONS DIAGRAM FOR BURNER PRIMARY CONTROLS Carlin 40200 Beckett 7505 Riello 530SE ...
Страница 45: ...43 ...
Страница 47: ...45 ...