Figure 19. Hand-Wrap Method for Pulling Cable
7. To re-route a cable with MPO connectors or a stub end with non-functional connectors to
the front of the panel:
a. Pull out enough cable to rotate the internal spool 90º as shown in
Figure 20. Pulling Microcable to Front of Panel for Front Routing
b. Remove the microcable from the rear cable retainer and then push the connectors back
into the space between the left side of the panel and the bulkhead panel. This will form
a slack loop at the front of the panel.
c. Pull on the slack loop to draw the connectors through to the front.
NOTE: TOP REMOVED TO SHOW
CABLE SPOOL TRAY AND MICRO-
CABLE ROUTING DETAIL
26150-A
STEP
b
: PUSH MICROCABLE INTO
CHASSIS TO FORM SLACK
LOOP AT FRONT OF PANEL
STEP
a
: ROTATE SPOOL UNTIL BULKHEAD
PANEL IS ALIGNED AS SHOWN
CONNECTORS
STEP
c
: PULL ON SLACK LOOP
TO DRAW CONNECTORS
TO FRONT OF PANEL