![CommScope 760242401 Скачать руководство пользователя страница 15](http://html1.mh-extra.com/html/commscope/760242401/760242401_user-manual_2643814015.webp)
TC-96292-IP
© 2020 CommScope, Inc. .
Page 15 of 22
numbering so that only the adhesive label numbers are visible and work your way downward
from top to bottom.
At the top of the rack, the silk-screened RU number 43 should correlate to the adhesive RU
number 40 and at the bottom of the rack, silk-screened RU number 4 should correlate to the
adhesive RU number 1. Repeat this procedure for the remaining rack rails
3.8 Installing Cable Managers and Accessories
Once the seismic rack is anchored in the floor, the cable manager and accessories can be
installed. Use the following procedure.
1.
Fasten the left and right cable managers to the frame, aligning the components as
shown in
Figure 15. Installing the Cable Managers
Note:
The fasteners should NOT be fully tightened until the lower troughs have been installed
so that they can be properly aligned.
27252-A
LEFT
CABLE
MANAGER
RIGHT
CABLE
MANAGER
WASHER
(6X EACH SIDE)
SPLIT LOCK WASHER
(6X EACH SIDE)
NUT
(6X EACH
SIDE)
WASHER (6X
EACH SIDE)
BOLT (6X EACH SIDE)
CABLE
MANAGER
ACCESSORY
RAILS
ALIGN
WITH BACK
BOLT POSITIONS
NOTE: NOT ALL
HOLES ARE USED
IN MID AND
UPPER
POSITIONS