Pole Mount Installation
1.
Locate the hoist plate and install, using the included hardware, to the top of the cabinet on the side that will be
closest to the pole.
2.
Locate the toothed bracket that has the mounting holes in the flange and mount it to the cabinet (below the previously
installed hoist plate) using the included hardware.
3.
Determine the top height of the cabinet. Drill a 5/8” hole 8 inches below the anticipated height of the cabinet, all the way
through the pole.
Note:
Clearfield does not provide the mounting hardware. Required hardware includes a 5/8” threaded rod (3” longer than
pole diameter), washers, lock washers, nuts and Lock Tight (red).
Note:
288 PON FSC cabinet shown for reference. Pre-Terminated FDH cabinet will be mounted to the pole using the same
method.