22
Catalyst 6509-NEB Switch and Cisco OSR-7609 Router Upgrade Note
78-16162-02
Verifying Installation
DC-Input Systems
To power up your DC-input system, follow these steps:
Step 1
Remove the tape from the circuit breaker switch handle, and restore power by moving the circuit breaker
switch handle to the On (|) position.
Step 2
Turn the power switch to the On (|) position on the power supply. Turning the power switch on also
engages a pawl that locks the power supply in the chassis.
Verifying Installation
After you have powered up the switch, verify the operation of the newly installed hardware as follows:
Step 1
Verify power supply operation by checking that the power supply front panel LEDs are in these states:
•
INPUT OK LED is green
•
FAN OK LED is green
•
OUTPUT FAIL LED is not lit
•
42V LED is green
If the LEDs indicate a power problem, refer to the installation guide for your hardware platform for
troubleshooting information.
Step 2
Verify the high speed fan tray operation by checking that the fan tray LEDs are in these:
•
INPUT POWER GOOD LED is green (there is one LED for each power input; if both inputs are
used, verify both LEDs)
•
FAN FAIL LED is green
If the LEDs indicate a problem, refer to the installation guide for your hardware platform for
troubleshooting information.
Step 3
Verify that the supervisor engine STATUS LED is lit. Check the STATUS LED periodically. If the
STATUS LED changes from orange to green, the supervisor engine has successfully completed the boot
process and is now online. If the STATUS LED remains orange or turns red, the supervisor engine has
not successfully completed the boot process and may have encountered an error.