18-67
Cisco ONS 15454 Procedure Guide, R5.0
March 2007
Chapter 18 DLPs A100 to A199
DLP-A195 Verify Timing in a Reduced Ring
Step 5
To clear a Force switch on the east line:
a.
Right-click the BLSR east port where you want to clear the protection switch and choose
Set East Protection Operation
. Ports with a Force switch applied are marked with an F.
b.
In the Set East Protection Operation dialog box, choose
CLEAR
from the drop-down list. Click
OK
.
c.
In the Confirm BLSR Operation dialog box, click
Yes
.
On the BLSR network graphic, a green and a purple span line connects each node. This is the normal
display for BLSRs when protection operations are not invoked.
Step 6
From the File menu, choose
Close
.
Step 7
Return to your originating procedure (NTP).
DLP-A195 Verify Timing in a Reduced Ring
Step 1
In node view, click the
Provisioning > Timing
tabs.
Step 2
Observe the Timing Mode field to see the type of timing (Line, External, Mixed) that has been set for
that node.
Step 3
Scroll down to the Reference Lists and observe the NE Reference fields to see the timing references
provisioned for that node.
Step 4
If the removed node was the only BITS timing source, perform the following:
a.
Contact your synchronization coordinator or appropriate personnel before continuing with this
procedure.
b.
Look for another node on the ring that can be used as a BITS source and set that node’s Timing Mode
to
External
. Choose that node as the primary timing source for all other nodes in the ring. See the
“DLP-A157 Change the Node Timing Source” task on page 18-24
c.
If no node in the reduced ring can be used as a BITS source, choose one node to be your internal
timing source. Set that node’s Timing Mode to
External
, set BITS-1 and BITS-2 BITS In State to
OOS
, and set the NE Reference to
Internal
. Then, choose line timing for all other nodes in the ring.
This forces the first node to be their primary timing source. (See the
Timing Source” task on page 18-24
Note
This type of timing conforms to Stratum 3 requirements and is not considered optimal.
Step 5
If the removed node was not the only BITS timing source, provision the adjacent nodes to line timing
using SONET links (east and west) as timing sources, traceable to the node with external BITS timing.
See the
“NTP-A28 Set Up Timing” procedure on page 4-9
.
Purpose
This task verifies timing in the ring where you removed a node.
Tools/Equipment
None
Prerequisite Procedures
DLP-A60 Log into CTC, page 17-66
Required/As Needed
As needed
Onsite/Remote
Onsite/remote
Security Level
Provisioning or higher
Содержание ONS 15454 Series
Страница 28: ...Tables xxviii Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 44: ...Tasks xliv Cisco ONS 15454 Procedure Guide R5 0 December 2004 ...
Страница 53: ...liii Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 55: ...lv Cisco ONS 15454 Procedure Guide R5 0 December 2004 About this Guide Document Conventions ...
Страница 126: ...4 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 4 Turn Up Node NTP A256 Set Up SNMP ...
Страница 168: ...5 42 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 5 Turn Up Network NTP A172 Create a Logical Network Map ...
Страница 304: ...10 8 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 10 Change Node Settings NTP A87 Change SNMP Settings ...
Страница 410: ...16 4 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Chapter 16 Power Down the Node NTP A114 Power Down the Node ...
Страница 510: ...17 100 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 17 DLPs A1 to A99 DLP A99 Determine Available VLANs ...
Страница 746: ...20 102 Cisco ONS 15454 Procedure Guide R5 0 March 2005 Chapter 20 DLPs A300 to A399 DLP A399 Install a UBIC H EIA ...
Страница 828: ...A 14 Cisco ONS 15454 Procedure Guide R5 0 December 2004 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 850: ...Index IN 22 Cisco ONS 15454 Procedure Guide R5 0 December 2004 description 4 11 remove 18 23 ...