About this Guide
The information in the book follows a task-oriented hierarchy using the elements described in the
following sections.
Chapter (Director Level)
The guide is divided into logical work groups (chapters) that serve as director entry into the procedures.
For example, if you are arriving on site after a contractor has installed the shelf hardware, proceed to
Chapter 2, “Install Cards and Fiber-Optic Cable”
and begin verifying installation and installing cards.
You may proceed sequentially (recommended), or locate the work you want to perform from the list of
procedures on the first page of every chapter (or turn to the front matter or index). describes the guide
chapters.
Table 1
Cisco ONS 15454 SDH Procedure Guide Chapters
Title
Summary
Chapter 1, “Install the Shelf and
FMECs”
Includes procedures for installing the shelf assembly, front
mount electrical connections (FMECs), fan-tray assembly,
LAN alarm and timing connections, electrical card cables, and
optional dense wavelength division multiplexing (DWDM)
equipment. Also included is the shelf installation acceptance
test.
Chapter 2, “Install Cards and
Fiber-Optic Cable”
Includes procedures to install common control cards, optical
cards, transponder and muxponder cards, electrical cards,
Ethernet cards and connectors, the FC_MR-4 card, and DWDM
cards. Also included are procedures for removing and replacing
a card, preprovisioning a slot, and installing and routing
fiber-optic cables.
Chapter 3, “Connect the PC and Log
into the GUI”
Includes procedures to install the Cisco Transport Controller
(CTC), set up a computer for different connection types, and
log into the Cisco ONS 15454 SDH.
Includes procedures to verify the card installation; create users
and assign security; set up name, date, time and contact
information; set up network access, firewall access, and timing;
create protection groups; and provision Simple Network
Management Protocol (SNMP).
Chapter 5, “Turn Up a Network”
Includes procedures to verify the node turn-up and to provision
and test the following networks: point-to-point, linear add/drop
multiplexing (ADM), multiplex section-shared protection ring
(MS-SPRing), and subnetwork connection protection (SNCP).
It also includes procedures for subtending rings.
Chapter 6, “Create Circuits and
Low-Order Tunnels”
Includes procedures to verify network turn-up; create manually
or automatically routed circuits or tunnels; create
unidirectional circuits with multiple drops; create half circuits,
Ethernet circuits, and overhead circuits; provision a DWDM
optical channel network connection (OCHNC); and create
virtual concatenated (VCAT) circuits.
Содержание ONS 15454 SDH
Страница 26: ...Tables vi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 ...
Страница 62: ...xxii Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 64: ...xxiv Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 66: ...xxvi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 414: ...16 4 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Chapter 16 Power Down the Node NTP D114 Power Down the Node ...
Страница 832: ...A 14 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 860: ...Index IN 28 Cisco ONS 15454 SDH Procedure Guide R6 0 78 17194 01 ...