Cisco ONS 15454 SDH Procedure Guide, R7.0
78-17194-01
Chapter 5 Turn Up a Network
NTP- D124 Provision a Point-to-Point Network
Step 4
Click the
Provisioning > General
tabs. Verify that all general node information settings match the
settings of your site plan. If not, see the
“NTP-D81 Change Node Management Information” procedure
Step 5
Click the
Provisioning > Timing
tabs. Verify that timing settings match the settings of your site plan.
If not, see the
“NTP-D85 Change Node Timing” procedure on page 11-6
Step 6
Click the
Provisioning > Network
tabs. Ensure that the IP settings and other CTC network access
information is correct. If not, see the
“NTP-D201 Change CTC Network Access” procedure on
.
Step 7
Click the
Provisioning > Protection
tabs. Verify that all protection groups have been created according
to your site plan. If not, see the
“NTP-D203 Modify or Delete Card Protection Settings” procedure on
.
Step 8
Click the
Provisioning > Security
tabs. Verify that all users have been created and their security levels
and policies match the settings indicated by your site plan. If not, see the
Change Security” procedure on page 11-7
Step 9
If SNMP is provisioned on the node, click the
Provisioning > SNMP
tabs. Verify that all SNMP settings
match the settings of your site plan. If not, see the
“NTP-D87 Change SNMP Settings” procedure on
.
Step 10
Provision the network using the applicable procedure shown in the
.
Stop. You have completed this procedure.
NTP-D124 Provision a Point-to-Point Network
Step 1
Complete the
“DLP-D60 Log into CTC” task on page 17-49
on an ONS 15454 SDH in the network
where you want to provision a point-to-point configuration.
Step 2
Click the
Provisioning > Protection
tabs. Verify that 1+1 protection is created for the STM-N cards.
Complete the
“DLP-D73 Create a 1+1 Protection Group” task on page 17-64
if protection has not been
created.
Step 3
Repeat Steps
and
for the second point-to-point node.
Step 4
Verify that the working and protect cards in the 1+1 protection groups correspond to the physical fiber
connections between the nodes, that is, verify that the working card in one node connects to the working
card in the other node, and that the protect card in one node connects to the protect card in the other node.
Purpose
This procedure provisions two ONS 15454 SDHs in a 1+1 point-to-point
(terminal) network.
Tools/Equipment
None
Prerequisite Procedures
NTP-D35 Verify Node Turn-Up, page 5-2
Required/As Needed
As needed
Onsite/Remote
Onsite
Security Level
Provisioning or higher
Содержание ONS 15454 SDH
Страница 26: ...Tables vi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 ...
Страница 62: ...xxii Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 64: ...xxiv Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 66: ...xxvi Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 About this Guide ...
Страница 414: ...16 4 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Chapter 16 Power Down the Node NTP D114 Power Down the Node ...
Страница 832: ...A 14 Cisco ONS 15454 SDH Procedure Guide R7 0 78 17194 01 Appendix A CTC Information and Shortcuts Equipment Inventory ...
Страница 860: ...Index IN 28 Cisco ONS 15454 SDH Procedure Guide R6 0 78 17194 01 ...