1-31
Cisco ONS 15310-MA SDH Procedure Guide, Release 9.1 and Release 9.2
78-19416-01
Chapter 1 Install the Cisco ONS 15310-MA SDH
Required Tools and Equipment
NTP-H164 Perform the Shelf Installation Acceptance Test
Step 1
Complete
by verifying that each procedure was completed.
Step 2
Check each wire and cable connection to make sure all cables are locked securely. If a wire or cable is
loose, return to the appropriate procedure in this chapter to correct it.
Step 3
Complete the
“DLP-H20 Measure Voltage” task on page 16-25
Stop. You have completed this procedure.
Purpose
Use this procedure to perform a shelf installation acceptance test.
Tools/Equipment
Voltmeter
Prerequisite Procedures
Applicable procedures in
Required/As Needed
Required
Onsite/Remote
Onsite
Security Level
Retrieve or higher
Table 1-3
ONS 15310-MA SDH Shelf Installation Task Summary
Description
Completed
NTP-H149 Unpack and Inspect the ONS 15310-MA SDH Shelf Assembly, page 1-4
NTP-H150 Install the Shelf Assembly, page 1-5
NTP-H169 Install the Cable Management Bracket, page 1-6
NTP-H167 Install the EIAs, page 1-10
NTP-H151 Install the Power and Ground, page 1-12
NTP-H152 Install the Fan-Tray Assembly, page 1-14
NTP-H153 Install the 15310E-CTX-K9 Cards, page 1-16
NTP-H154 Install the Ethernet Cards, page 1-19
NTP-H155 Install the Electrical Cards, page 1-23
NTP-H156 Install the Filler Cards, page 1-25
NTP-H157 Install Wires to Alarm, Timing, Craft, LAN, and UDC Pin Connections,
page 1-26
NTP-H158 Install the Electrical Cables, page 1-27
Содержание ONS 15310-MA SDH
Страница 20: ...Figures xx Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 ...
Страница 45: ...xlv Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Preface ...
Страница 48: ...xlviii Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Preface ...
Страница 290: ...15 4 Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Chapter 15 Power Down the Node ...