Cisco ONS 15310-MA SDH Procedure Guide, Release 9.1 and Release 9.2
78-19416-01
Chapter 13 Add and Remove Nodes
Before You Begin
Step 5
Complete the
“DLP-H52 Provision Section DCC Terminations” task on page 16-68
for the working
STM-M port at the new node. Make sure to set the Port State in the Create RS-DCC Termination dialog
box to
unlocked
. (Do not create a DCC termination on the protect port.)
Note
DCC failure alarms appear after you create DCC terminations in the linear ADM node until you
connect the fiber during
.
Step 6
Complete the
“DLP-H29 Log into CTC” task on page 16-43
at the linear ADM node that will connect
to the new node. If you are already logged in, continue with
Step 7
Complete the
“DLP-H163 Check the Network for Alarms and Conditions” task on page 17-56
.
Step 8
Install the STM-M port that will connect to the new node. See
“DLP-H16 Install SFP Connectors” task
. If the ports are already installed, continue with
Note
If the new node is not an ONS 15310-MA SDH, refer to the corresponding user documentation
for installation procedures.
Step 9
Connect the working port at the existing linear ADM node to the working port at the new node. See
“DLP-H18 Install Fiber-Optic Cables in a 1+1 Configuration” task on page 16-21
Step 10
Connect the protect port at the existing linear ADM node to the protect port at the new node.
Step 11
Complete
NTP-H142 Create Protection Groups for ONS 15310-MA SDH, page 3-10
for the two STM-M
ports that connect to the new node.
Step 12
Complete the
“NTP-H142 Create Protection Groups for ONS 15310-MA SDH” procedure on page 3-10
for the two STM-M ports that connect to the new node.
Step 13
Complete the
“DLP-H52 Provision Section DCC Terminations” task on page 16-68
for the working
STM-M port that connects to the working port on the new node. Make sure to set the Port State in the
Create RS-DCC Termination dialog box to
unlocked
. (Do not create a DCC termination for the protect
port.)
Step 14
From the View menu, choose
Go to Network View.
Verify that the newly created linear ADM
configuration is correct. A green span line should appear between each linear node.
Step 15
Complete the
“DLP-H163 Check the Network for Alarms and Conditions” task on page 17-56
to verify
that no unexpected alarms or conditions are present.
Stop. You have completed this procedure.
NTP-H135 Add a Non-ONS 15310-MA Node to a Linear ADM
Purpose
This procedure adds an ONS 15600, ONS 15454, or ONS 15310-MA
SDH between two nodes in a 1+1 configuration. The ONS 15310-MA
SDH has four optical ports and can be added as a middle node.
Tools/Equipment
None
Содержание ONS 15310-MA SDH
Страница 20: ...Figures xx Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 ...
Страница 45: ...xlv Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Preface ...
Страница 48: ...xlviii Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Preface ...
Страница 290: ...15 4 Cisco ONS 15310 MA SDH Procedure Guide Release 9 1 and Release 9 2 78 19416 01 Chapter 15 Power Down the Node ...