Feeder Line Assembly and Suspension
LIBERTY® Feeding System with Electronic Sensor (ES)
28
Attaching Feeder Lift Cords to the Actuator Cable
With both ends of the Cable securely anchored and Spring stretch set, run the Actuator up and down 2 to 3 times.
Return the actuator to A position. Using the Lift Cords raise the Feed Cone then return it to the down
position.Starting at the Winch, pull the support Cone toward the actuator, then apply equal pressure to the Lift
Cords then connect the Lift cords to the Lift Cable (Do not lift the Feed Cone off the support tabs). The Cords
must be routed toward the Actuator (center of the brood area). Lift the Feed Cone to connect Cords
See
for the proper way of connecting the Cords to the Cable. Place the Cord in the Clamp (13057)
bottom, then place the cable on top of the Cord. Finally, install the Clamp top.
Note:
Both the end and mid-line
Control will have manual
ALL-OUT™ feed flooding.
Support Cone pulled toward
the Actuator
Figure 51.Connecting the Support Cords
Do not lift Feed Cone off the stop
on the leg. Hold the Cone down when
connecting the Lift Cords to the Cable.
Figure 52.Cable Clamp installation detail.
Clamp Top
Clamp
Bottom