Section 2 - Location and Foundation
3. Place a level on the back of the burner auger motor
as shown in Fig. 7. The back of the transition box
should be slightly higher than the front, indicated
when the level is vertical and there is a small gap
(from 1/16" to 3/32", or 1.6 mm to 2.4 mm) between
the level and the top of the burner auger motor and
no gap between the level and the bottom of the
burner auger motor.
Fig. 7
Small Gap
(No less
than 1/16")
Place Decal
Here
No Gap
Centered
Shims
Use shims to position
feed assembly as shown.
NOTE
Foundation
Foundation
Shim
(Shown in black)
Maxim Leveling Procedure
© 2014 Central Boiler
Foundation
4. Use shims as necessary under the outdoor furnace
in the locations shown until the procedure in Step
3 indicates that the back of the transition box is
slightly higher than the front.
NOTE: Periodically check that the outdoor furnace
is leveled as described in these instructions
because frost can cause the foundation to move.
5. Install the access panels on the back corner of the
furnace.
6. Connect the electrical power at the main power
source and turn on the gas supply at the appliance
service valve.
7. Connect the electrical power at the main power
source and turn on the gas supply at the appliance
service valve.
Clearances
NOTE: Clearance to combustibles from the
chimney transition box is 8" (20 cm); HOWEVER,
if installing with the back of the outdoor furnace
facing an immovable wall, object, etc., you
must maintain 36" (91.5 cm) of clearance to the
wall, object, etc. in order to perform periodic
maintenance (see Fig. 8).
Fig. 8
WARNING
Maintain the following clearances from
combustibles for the outdoor furnace
installation:
• 8" (20 cm) from the transition box
• 6" (15 cm) from the sides
• 48" (122 cm) from the front
• 8" (20 cm) from the chimney
• 27" (68.5 cm) from the top
• The foundation must be noncombustible