Special vacuum drying
The special vacuum drying method shall be
adopted when:
Finding moisture during flushing refrigerant
pipe.
Conducting construction on rainy day,
because rain water might penetrated into
pipeline.
Construction period is long, and rain water
might penetrated into pipeline.
Rain water might penetrate into pipeline
during construction.
Procedures of special vacuum drying are as
follows:
Vacuum drying for 1 hour.
Vacuum damage, filling nitrogen to reach
0.5Kgf/cm2 .
Because nitrogen is dry gas, vacuum
damage could achieve the effect of
vacuum drying, but this method could not
achieve drying thoroughly when there is
too much moisture. Therefore, special
attention shall be drawn to prevent the
entering of water and the formation of
condensate water.
Vacuum drying again for half an hour.
If the pressure reaches -755mmHg,start
to pressure leakage test. If it cannot reach
the value, repeat vacuum damage and
vacuum drying again for 1 hour.
Leakage test: After the vacuum degree
reaches -755mmHg, stop vacuum drying
and keep the pressure for 1 hour. If the
indicator of vacuum gauge does not go up,
it is qualified. If going up, it indicates that
there is moisture or leak source.
13.7 Additional refrigerant charge
After the vacuum drying process is carried
out, the additional refrigerant charge
process needs to be performed.
The outdoor unit is factory charged with
refrigerant.
The
additional
refrigerant
charge volume is decided by the diameter
and length of the liquid pipe between indoor
and outdoor unit. Refer the following
formula to calculate the charge volume.
Diameter
of
liquid
pipe
(mm)
Φ6.35
Φ9.52
Formula
V=15g/m×(L-7.5)
V=30g/m×(L-7.5)
V:
Additional refrigerant charge volume (g).
L:
The length of the liquid pipe (m).
Note:
Refrigerant may only be charged after
performed the vacuum drying process.
Always use gloves and glasses to protect
your hands and eyes during the charge
work.
Use electronic scale or fluid infusion
apparatus to weight refrigerant to be
recharged. Be sure to avoid extra
refrigerant charged, it may cause liquid
hammer of the compressor or protections.
Use supplementing flexible pipe to connect
refrigerant cylinder, pressure gauge and
outdoor unit. And The refrigerant should be
charged in liquid state. Before recharging,
The air in the flexible pipe and manifold
gauge should be exhausted.
After finished refrigerant recharge process,
check whether there is refrigerant leakage
at the connection joint part. (Using gas
leakage detector or soap water to detect).
13.8 Engineering of insulation
13.8.1
Insulation of refrigerant pipe
1
Operational procedure of refrigerant
pipe insulation
Cut the suitable pipe → insulation (except joint
section) → flare the pipe → piping layout and
connection→ vacuum drying → insulate the
joint parts
Содержание 38QUA009DS
Страница 8: ...5 2 2 Part names of Indoor Outdoor units Cassette Unit...
Страница 9: ...6 A5 Ducted Units A6 Ducted Units...
Страница 10: ...7 Floor ceiling Units...
Страница 11: ...8 HESP DUCTED Units...
Страница 35: ...32 6 Wiring Diagram 6 1 Indoor Unit 40QTD018DS 40QTD024DS 40QTD036DS 40QTD048DS...
Страница 36: ...33 40QSM018DS 40QSM024DS 40QSM036DS 40QSM048DS...
Страница 37: ...34 40QZL018DS 40QZL024DS 40QZL036DS...
Страница 38: ...35 40QZL048DS 40QZL060DS...
Страница 40: ...37 6 2 Outdoor Unit 38QUA018DS 38QUA024DS...
Страница 41: ...38 38QUA036DS...
Страница 42: ...39 38QUA048DS 38QUA060DS...
Страница 44: ...41 40QSM018DS Code 0 Code 1 Code 2 Code 3 Code 4...
Страница 45: ...42 40QSM024DS Code 0 Code 1 Code 2 Code 3 Code 4...
Страница 46: ...43 40QSM036DS Code 0 Code 1 Code 2 Code 3 Code 4...
Страница 47: ...44 40QSM048DS Code 0 Code 1 Code 2 Code 3 Code 4...
Страница 60: ...57 12 Field Wiring 18K 24K 36K 48K...
Страница 61: ...58 60K...
Страница 104: ...101 P U P V...
Страница 105: ...102 P W P N...