Installation Instructions
SECTION NINE
To Install the Appliance
EXAMINE FLUE / CHIMNEY
Check that the flue/chimney conforms to the required specifications as previously stated.
Examine the condition and carry out any remedial work. If the flue/chimney has been used for
solid fuel or oil, it should be swept prior to appliance installation. A smoke test must be carried
out to check that satisfactory smoke clearance has been established. If all the smoke is not
drawn into the flue, pre-heat the flue with a blowtorch or similar and re-check. If there is any
uncertainty examine for the cause and, if necessary, seek expert advice.
PREPARING FOR INSTALLATION
•
Remove the battery compartment by lifting it out of
the firebox.
•
Remove the top grille from the fire by removing the 4
securing screws.
•
Remove the burner unit by lifting it out right hand
side first.
•
Remove
the
four
screw
securing
the
heatshield/burner support to the carrier assembly
and lift out the heatshield RH side first.
CONNECTING THE GAS SUPPLY
The gas supply is to be connected to the appliance from the rear right or underside right of the
unit as a concealed fixing only.
DO NOT cut holes into
the bottom or sides of the outer box – use the
purpose provided seal and gas pipe entry as it will
ensure the best protection against flue draught
causing component damage and overheating under
the burner.
Route 8mm O/D half hard copper tube to the rear right
side of the fireplace opening, taking into account the
requirements of BS 6891 1988 dealing with enclosed
pipes.