5 Commissioning Inverter
5.1 Electrical Inspection
1) The inverter DC switch and external circuit breaker are disconnected
2) The inverter should be accessible for operation, maintenance and service.
3) Nothing is left on the top of the inverter.
4) The inverter is correctly connected to the external devices, and the cables are routed in a safe place or protected against
mechanical damage.
5) The selection of the AC circuit breaker is in accordance with the user manual and all applicable local standards.
6) All unused terminals at the bottom of the inverter are properly sealed.
7) Warning signs & labels are suitably affixed and durable.
5.2 Commissioning Procedure
If all of the items mentioned above meet the requirements, proceed as follows to start up the inverter for the first time.
Step 1: Rotate the DC switch of the inverter to "ON" position.
Step 2: Connect the AC switch (if applicable) between the inverter and the grid.
Step 3: Connect the DC switch (if applicable) between the inverter and the PV string.
Step 4: Set initial protection parameters via the CSI Smart Energy App. If the irradiation and grid conditions meet requirements,
the inverter will normally operate.
Step 5: Observe the LED indicator to ensure that the inverter operates normally.
No.
Description
Indicator Light Status
Flicker Frequency
1
wait
green light blinks
1 second on, 1 second off
2
normal
green light
/
3
error
red light
/
6 CSI Smart Energy App - Local Mode
6.1 APP Introduction
The CSI SmartEnergy APP can establish a communication connection to the dongle via the Bluetooth, thereby achieving local
access to the inverter. Users can use the App to view basic information, alarms , set parameters, etc.
6.2 Download and Install the App
Method 1
:
Scan the following QR Code to download and install the App according to the prompt information.
Method 2: For the monitoring and local APP information, please refer to documents published on our website at:
https://smartenergy.csisolar.com
Содержание CSI-15K-T4001A-E
Страница 2: ......