CSI GRID-TIED PV INVERTER

INSTALLATION AND OPERATION MANUAL 

www.csisolar.com

CSI Solar Co., Ltd.  
199 Lushan Road, SND, Suzhou, Jiangsu, China, 215129 

CSI-100K-T400GL02-E | CSI-110K-T400GL02-E

CSI-100K-T400GL02-ZA | CSI-110K-T400GL02-ZA

Version 1.3, Release Date: 05,2022

Global Headquarters

CSI Solar Co., Ltd.  
199 Lushan Road, SND, Suzhou, Jiangsu, China, 215129
P +1 519 837 1881
F +1 519 837 2550
Sales Inquiries Email: [email protected]
Customer Support Email: [email protected]

 

Australia

Canadian Solar MSS (Australia) Pty Ltd
44 Stephenson St, Cremorne VIC 3121, Australia
P +61 ( 3 ) 860 918 44
Sales Inquiries Email: [email protected]
Customer Support Email: [email protected]

South East Asia

101 Thompson Road #15-03 United Square, Singapore 307591
P +65 6572 905 
F +65 6559 4690
Sales Inquires Email: [email protected]
Customer Support Email: [email protected]

Latin America

Canadian Solar Brazil
Avenida Roque Petroni Junior, 999, 4º andar Vila Gertrudes, 
São Paulo, Brasil,CEP 04707-910
P +55 11 3957 0336
Sales Inquiries Email:[email protected]
Customer Support Email: [email protected]

Please adhere to the actual products in case of any discrepancies in this user manual. 

This manual is subject to change without prior notification. Copyright is reserved. 
Duplication of any part of this issue is prohibited without written permission.

 

 

Europe, Middle East & Africa

Canadian Solar EMEA GmbH
Radlkoferstrasse 2, 81373 Munich, Germany
P +49 (0) 89 519 968 90
F +49 (0) 89 519 968 911
Sales Inquiries Email: [email protected]
Customer Support Email: [email protected]

Содержание CSI-100K-T400GL02-E

Страница 1: ...01 Thompson Road 15 03 United Square Singapore 307591 P 65 6572 905 F 65 6559 4690 Sales Inquires Email sales sg csisolar com Customer Support Email service cn csisolar com Latin America Canadian Solar Brazil Avenida Roque Petroni Junior 999 4º andar Vila Gertrudes São Paulo Brasil CEP 04707 910 P 55 11 3957 0336 Sales Inquiries Email sales br csisolar com Customer Support Email service latam csis...

Страница 2: ...2 Shutdown procedure 37 37 37 7 1 Main Menu 38 38 7 2 Information 4 1 RS485 Communication 28 7 Normal operation 38 4 2 PLC Communication 30 26 3 4 4 Meter Connection optional 4 3 Logic interface connection 32 7 3 1 Set Time 40 7 3 Settings 40 7 3 2 Set Address 40 7 4 Advanced Info Technicians Only 41 7 4 1 Alarm Message 41 7 4 2 Running Message 41 7 4 3 Version 42 7 4 4 Daily Energy 42 7 4 5 Month...

Страница 3: ...an Solar Three phase Inverters covert DC power from the photovoltaic PV array into alternating current AC power that can satisfy local loads as well as feed the power distribution grid This manual covers the three phase inverter model listed below CSI 100K T400GL02 E CSI 110K T400GL02 E The following two models are specially supplied for South Africa market CSI 100K T400GL02 ZA CSI 110K T400GL02 Z...

Страница 4: ...er seal with adhesive tape with the desiccant inside the box Store the inverter in a clean and dry place free of dust and dirt The storage temperature must be between 40 70 and humidity should be between 0 to 95 non condensing Do not stack more than four 4 inverters high on a single pallet Keep the box es away from corrosive materials to avoid damage to the inverter enclosure Inspect the packaging...

Страница 5: ...ter is to be installed in a confined space Figure 3 1 Distances required between inverters NOTE Nothing should be stored on or placed against the inverter 3 Installation WARNING Risk of fire Despite careful construction electrical devices can cause fires Do not install the inverter in areas containing highly flammable materials or gases Do not install the inverter in potentially explosive atmosphe...

Страница 6: ...terminals communication waterproof connectors to prevent the cables from sagging and causing the waterproof connectors to loosen Tilt angle 15 Ground clearance 300mm 3 1 2 Installation environment requirements Avoid Direct Sunlight Installation of the inverter in a location exposed to direct sunlight should be avoided Direct exposure to sunlight could cause Inverter temperature rises Output power ...

Страница 7: ...ed vertically The steps to mount the inverter are listed below 1 Refer to Figure 3 6 drill holes for mounting screws based on the hole diameter of bracket using a precision drill keeping the drill perpendicular to the wall Max depth is 90mm 2 Make sure the bracket is horizontal And the mounting holes in Figure 3 6 are marked correctly Drill the holes into wall at your marks 3 3 1 Wall mounting 3 U...

Страница 8: ...s from vertical Figure 3 10 Wrong installation Angle The steps to mounted to the rack are listed below 3 Install mounting plate 1 Remove the bracket and fasteners from the packaging Mark the position for hole drilling according to the hole positions of the bracket Figure 3 11 Mark the position for hole 2 Drill the marked holes It is recommended to apply anti corrosive paint at the hole for corrosi...

Страница 9: ...C OFF 2 Switch the DC Isolator OFF 3 Connect the inverter to the grid 4 Assemble PV connector and connect to the Inverter Inverter design uses PV style quick connect terminal The top cover needn t be opened during DC electrical connection The labels located the bottom of the inverter are described below in table 3 1 All electrical connections are suitable for local or national standard Table 3 1 E...

Страница 10: ...unding 2 Prepare OT terminals M10 To effectively protect the inverter two grounding methods must be performed Connect the AC grounding cable Please refer to section 3 4 3 Connect the external grounding terminal 1 Prepare the grounding cable recommend to use the outdoor copper core cable The grounding wire should be at least half size of the hot wires To connect the grounding terminal on the heat s...

Страница 11: ... of connector and tighten nut with torque 3 4 Nm Please see table 3 1 for acceptable wire size for DC connections Wire must be copper only WARNING DO NOT connect the PV array positive or PV array negative cable to ground This can cause serious damage to the inverter WARNING MAKE SURE the polarity of the PV array output conductors matches the DC and DC terminal labels before connecting these conduc...

Страница 12: ...en the inverter and the grid NOTE Use AL CU transfer bi metallic terminal or anti oxidant grease with aluminum cables and terminals 3 4 3 1 Connecting the inverter to the utility grid All electrical installations must be carried out in accordance with the local standards and the National Electrical Code ANSI NFPA 70 or the Canadian Electrical Code CSA C22 1 The AC and DC electric circuits are isol...

Страница 13: ...igure 3 28 Wiring without Neutral Cable specification 70 38 56 45 Copper cored cable Cable outer diameter mm Traverse cross sectional area mm 2 Range Recommended 35 185 Range Recommended NOTE If chosing aluminum alloy cable you must use copper aluminum transfer terminal in order to avoid direct contact between copper bar and Aluminum alloy cable Please select a copper aluminum transfer terminal ba...

Страница 14: ...d DTSD1352 External CT Type Customer can place the order for a suitable meter from Canadian Solar Sales Reps Below are the connection diagrams of different meters connecting to different locations Detailed settings please refer to Section 7 5 11 27 26 L1 L2 L3 N PE Load Figure 3 29 External CT Type Meter Meter in Grid INV L1 INV L2 INV L3 INV N INV PE Grid L1 Grid L2 Grid L3 Grid N Grid PE UaUbUc ...

Страница 15: ...Figure 4 3 Strip the insulation layer and connect to RJ45 plug Correspondence between the cables and the stitches of plug Pin 1 white and orange Pin 2 orange Pin 3 white and green Pin 4 blue Pin 5 white and blue Pin 6 green Pin 7 white and brown Pin 8 brown Pin 1 with 4 and 2 with 5 are used for communication connection Pin 1 and 4 are connected with RS485 A Pin 2 and 5 are connected with RS485 B ...

Страница 16: ...cation One of the RS485 and PLC communication methods is available For the models with additional PLC communication switching between PLC communication and RS485 communication can be realized by flipping the switch on the communication board as indicated in figure 4 7 Only one communication method is available during operating Standard model without PLC communication doesn t have this switch NOTE ...

Страница 17: ...rd be verified for the country of installation before commissioning The menu for changing the grid standard or for creating a custom standard is accessible as described in Section 6 7 and below WARNING Failure to set the correct grid standard could result in improper operation of the inverter inverter damage or the inverter not operating at all 5 2 Changing the grid standard 5 2 1 Procedure to set...

Страница 18: ...inverter see Specifications in section 10 may damage the inverter Although Canadian Solar inverters feature reverse polarity protection prolonged connection in reverse polarity may damage these protection circuits and or the inverter 5 4 3 2 Leakage to ground Measure leakage to ground to check for a DC ground fault 3 Use the UP DOWN keys to highlight the SELECT STANDARD option Press enter to selec...

Страница 19: ... POWER LED and LCD will be continuously lit 4 Canadian Solar inverters are powered from the DC side When the inverter detects DC power that is within start up and operating ranges the inverter will turn on After turn on the inverter will check internal parameters sense and monitor AC voltage hertz rate and the stability of the supply grid During this period the green OPERATION LED will flash and t...

Страница 20: ..._Power Shows the apparent power of the inverter Work Mode Volt watt DRM NO 08 10 sec 10 sec Work Mode Shows current working mode DRM NO Shows DRM Number I_DC01 Shows input 01 current value I_DC02 Shows input 02 current value I_DC20 Shows input 20 current value VPV_Total 1000 0V IPV_Total 99 0A V_A 345 7V I_ A 109 0A V_C 345 0V I_ C 109 8A In normal operation LCD screen alternatively shows inverter...

Страница 21: ...essage 2 Running message 3 Version 4 Daily Energy 5 Monthly Energy 6 Yearly Energy 7 Daily Records 8 Communication Data 9 Warning Message The following submenus are displayed when the Settings menu is selected 1 Set Time 2 Set Address 7 3 Settings 7 3 1 Set Time This function allows time and date setting When this function is selected the LCD will display a screen as shown in Figure 7 3 NEXT ENT O...

Страница 22: ...ory of changing settings Only for maintance personel 7 Normal operation 7 Normal operation 7 4 3 Version The screen shows the model version of the inverter And the screen will show the software ver by pressing the UP and DOWN at the same time see Figure 7 7 7 4 4 Daily Energy The function is for checking the energy generation for selected day Figure 7 8 Select date for daily energy YES ENT NO ESC ...

Страница 23: ...erence standard see Figure 7 16 YES ENT NO ESC Standard G99 Figure 7 16 Selecting the User Def menu will access to the following submenu see Figure 7 17 Figure 7 17 OV G V1 400V OV G V1 T 1 0S Below is the setting range for User Def Using this function the limits can be changed manually These voltage values are the phase voltage Table 7 2 Ranges for User Def NOTE The initial value of the User Def ...

Страница 24: ...key to move the cursor Press the UP key to revise the value Press the ENTER key to execute the setting Press the ESC key to return to the previous menu 7 5 4 Reset Password This function is used to set the new password for menu Advanced info and Advanced information see Figure 7 19 Figure 7 19 Set new password YES ENT NO ESC Password 0000 Enter the right password before set new password Press the ...

Страница 25: ...ckflow Figure 7 24 Press the UP DOWN keys to set data Press the ENTER key to set backflow power Then press DOWN keys to move the cursor press UP to change the number Press the ESC key to save the settings and return to the previous menu The setting is used to define the allowed export power into the grid The setting range is between 00000W to 29900W YES ENT NO ESC Power 00000W Select EPM Settings ...

Страница 26: ...nverter will stop generation and give Failsafe alarm on the LCD When the failsafe function is OFF and CT Meter is disconnected somehow the inverter will keep the output power as the last moment when the CT Meter is still connected After a restart the inverter will output at full power without limit 7 Normal operation 7 Normal operation Mode 02 As shown in the figure 7 29 the per phase limiting mod...

Страница 27: ...e previous menu 7 5 18 I V Curve This function is used to scan the I V characteristic curves of each PV strings Figure 7 34 I V Curve Set I V Curve I V Curve Scan 7 5 16 DSP Update The function is used for update the DSP This function is applicable by maintenance personnel only wrong operation will prevent the inverter from reaching maximum power 7 5 17 Compensation Set The screen shows Figure 7 3...

Страница 28: ...Set AFCI AFCI ON OFF AFCI Level ON OFF Warning The AFCI Level is reserved for Canadian Solar technicians ONLY Do not change the sensitivity otherwise it will lead to frequent false alarms or malfunctions Canadian Solar is not responsible for any further damages caused by unauthorized modifications NOTE The setting corresponds to the current status as well which can be used to inspect the ON OFF st...

Страница 29: ...ing 450 Vdc between PV and ground No need any control or settings The Anti PID module repairs the PID effect of the PV model at night When operating the inverter LCD screen displays PID repairing information and the red light is on The Anti PID function is always ON when AC is applied If maintenance is required and turn off the AC switch can disable the Anti PID function 8 Maintenance 6 Disconnect...

Страница 30: ...ction 2 Check driver connection UN G V01 02 DC INTF DC input overcurrent 1 Restart inverter 2 Identify and remove the string to the fault MPPT 2 Change power board IGFOL F Grid current tracking fail OV G I Over grid current OV DCA I IGBT OV I Over IGBT current 1 Restart inverter or contact installer IG AD Grid current sampling fail 9 Troubleshooting Table 9 1 Fault message and description 1 Remove...

Страница 31: ...ensions W H D Weight 1065 567 344 5mm 84kg Max DC input voltage Volts MPPT voltage range Volts Max input current Amps MPPT number Max input strings number Rated grid voltage Volts Rated grid output current Amps Power Factor at rated output power Max efficiency EU efficiency Model Topology Self consumption night Operating ambient temperature range Relative humidity Ingress protection Cooling concep...

Страница 32: ...g frequency range Hertz 45 55 or 55 65 2W Noise emission typical 65 dBA Intelligent redundant cooling CSI 110K T400GL02 E Dimensions W H D Weight 1065 567 344 5mm 84kg Max DC input voltage Volts MPPT voltage range Volts Max input current Amps MPPT number Max input strings number Rated grid voltage Volts Rated grid output current Amps Power Factor at rated output power Max efficiency EU efficiency ...

Страница 33: ...wer Watts Max output power Watts Max apparent output power VA 600 110000 121000 121000 167 1 158 8 183 8 THDi at rated output power 3 Start up voltage Volts Max short circuit input current Amps Rated DC voltage Volts Rated grid frequency Hertz 180 1000 195 Max output current Amps AC connection DC connection Display Communication connections MC4 connector OT Terminal max 185 mm LCD 2 20 Z RS485 Opt...

Страница 34: ... 135000 for VDE AR N 4105 66 67 11 Declarations 11 Declarations 11 1 REACH Declaration ...

Страница 35: ... 68 69 11 2 CE and RoHS Declaration 11 Declarations 11 Declarations ...

Страница 36: ...11 Declarations 70 ...

Страница 37: ...earances and are properly ventilated Completed 5 Serial number Record the product serial numbers located on the side label Serial Numbers attached list 6 Solar modules Confirm PV module installation completion Record the total power of the PV modules Completed Record kWp in Notes 7 DC input and AC output connection Switch off the DC and AC distribution unit connect DC to PV terminals of inverter an...

Страница 38: ...us in Notes 1 Switch the grid supply main Switch AC ON first 2 Switch the DC switch ON If the voltages of PV arrays are higher than start up voltage the inverter will turn on The red LED power will be continuously lit 3 When both the DC and the AC sides supply to the inverter it will be ready to generate power Initially the inverter will check both its internal parameters and the parameters of the...

Страница 39: ...g the front panel interface Completed Record current date time in Notes 6 Communication setting if avail Set communication with a unique address for each inverter Completed Record address in Notes 7 Machine version For maintenance and reference please record the firmware revisions if applicable Completed Record with serial numbers 8 Operating parameter Completed Record operating parameters in Note...

Страница 40: ...tilt Output power Input DC voltage Insulation Resistance kOhm PV start up voltage Grid V Max V Min Frequency Max Min Power Factor PF Configuration MPPT Individual MPPT Parallel Monitoring RS485 Ethernet Monitoring equipment and supplier PV module manufacturer PV model DC cable size AC cable size Transformer ratings supplier Number of series connected modules in PV strings Number of PV strings in p...

Страница 41: ...rior to inverter site selection and installation 3 PHASE STRING INVERTERS CSIF ST 016 A 0 INSTALLER S NAME INSTALLER S SIGNATURE COMPANY DATE Inverter serial numbers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 Please return completed form to service emea csisolar com www csisolar com SERIES ...