Fireplace Concrete Pad Construction:
Call 811 for information on underground utility marking. Select desired location and excavate
64” L x 58” W x 12” D area for concrete pad. Fill excavated area with approximately 6” of ¾”
clean gravel, compacting every 3”. Frame remaining 4” with 2”x4” lumber to create a level pad
(be sure 2”x4” wood frame is perfectly level, front to back and side to side). See attached
drawing for details of steel reinforcement rod placement. Fill concrete tubes and 2”x4” wood
frame with a 4,000 psi strong concrete mix.
* Allow concrete pad to cure for 48 hours.
Construccion Concreta del Cojín de la Chimenea:
Llame al 811 para obtener informaci n sobre la utilidad de metro marcado. Seleccione la ubicaci
n deseada y excavar 88” de largo x 60” W x 12” D área de plataforma de concreto. Instale cuatro
8” de diámetro de los tubos de hormig n a las heladas-line como por el c digo local. Llene la zona
excavada con aproximadamente 6” de ¾” limpia grava, compactando cada 3”. (No llene los
tubos de concreto con grava). Marco restantes 4” con 2” x4”de madera para crear una plata-
forma de nivel. (Asegúrese de 2” x 4” marco de madera está perfectamente horizontal, de ade-
lante hacia atrás y de lado a lado) Véanse los detalles del dibujo para la colocaci n de varillas de
acero de refuerzo. Relleno de concreto y tubos de 2” x4” marco de madera con una mezcla de
concreto 4000 PSI fuerte.
* Deje que la almohadilla para curar por un mínimo de 48 horas.