Installing the IRM3 into an MMAC Chassis
IRM3 User’s Guide
Page 3-5
Figure 3-2
IRM3 Installation
3. Secure the module to the MMAC by turning the knurled knobs. Be
sure that the module is firmly attached to the MMAC. Failure to do so
may result in improper operation.
4. Power on the MMAC.
5. Observe the status of the LANVIEW LEDs on the IRM3. See
Figure 3-3. After approximately 2 seconds, the LEDs should be in the
following conditions:
•
PWR lit, indicating that the IRM3 is receiving power.
•
POK lit, indicating that the network interface chip associated with
the IRM3 internal repeater ports have passed the internal loopback
test and are now ready for transmission.
•
BOK lit, indicating the IRM3 is operating properly.
WARNING
Fill all open slots in the MMAC hub with blank plates. If the
plates are not installed, the MMAC may fail to comply with
allowed limits of conducted and radiated emissions.
KNURLED
KNOBS
IRM-3
MMAC-8
BOARD SLOT 1
0494105