7 | Maintenance
14 / 24
Instruction Manual R5 RA_RC 0010-0016 C_EN_en
• Shut down the machine and lock against inadvertent start up.
• Vent the connected lines to atmospheric pressure.
If necessary:
• Disconnect all connections.
7.1 Maintenance Schedule
The maintenance intervals depend very much on the individual operating conditions. The
intervals given below are considered as starting values which should be shortened or ex-
tended as appropriate. Particularly harsh applications or heavy duty operation, such as high
dust loads in the environment or in the process gas, other contamination or ingress of pro-
cess material, can make it necessary to shorten the maintenance intervals significantly.
Maintenance work
Interval
Normal application
Harsh application
.
Daily
• Check the machine for oil leaks - in case of
leaks have the machine repaired
(contact Busch).
In case an inlet filter is installed:
• Check the inlet filter cartridge, replace it if
necessary.
Monthly
• Change the oil*, the oil filter* (OF) and
the exhaust filters (EF).
Max. after 4000
hours, at the latest
after 1 year
Max. after 2000
hours, at the latest
after 6 months
• Clean the machine from dust and dirt.
In case of a gas ballast valve (GB) being in-
stalled:
• Clean the gas ballast valve.
If the machine is equipped with an air-oil
heat exchanger (AHE):
• Check and/or clean the air-oil heat ex-
changer.
Every 6 months
• Contact Busch for an inspection.
If required, overhaul the machine.
Every 5 years
* Service interval for synthetic oil, shorten the interval when using mineral oil, contact
Busch Service
7.2 Oil Level Inspection
• Shut down the machine.
• When the machine is stopped, wait 1 minute before checking the oil level.
MAX
MIN
MAX
MIN
MAX
MIN
• Fill up if necessary, see