Maintenance | 7
0870572700_RD0200-0360A_-0003_IM_en
17 / 28
• Shut down the machine and lock against inadvertent start up.
• Vent the connected lines to atmospheric pressure.
Version with water-oil heat exchanger:
• Turn off the water supply.
If necessary:
• Disconnect all connections.
7.1 Maintenance Schedule
The maintenance intervals depend very much on the individual operating conditions. The
intervals given below are desired to be considered as starting values which should be
shortened or extended as appropriate. Particularly harsh applications or heavy duty oper-
ation, such as high dust loads in the environment or in the process gas, other contamina-
tion or ingress of process material, can make it necessary to shorten the maintenance in-
tervals significantly.
Maintenance work
Interval
Normal application
Harsh application
Daily
• Check the machine for oil leaks - in case of
leaks have the machine repaired (contact
Busch).
In case of an inlet filter being installed:
• Check the inlet filter cartridge, replace if
necessary.
Monthly
• Change the oil, the oil filter (OF) and the
exhaust filter (EF).
• Clean the machine and air heat exchanger
).
• Clean the gas ballast valve (GB).
Max. after 4000
hours, at the latest
after 1 year
For RD 0200 A:
max. after 3600 hours,
at the latest after 6
months
For RD 0240 A:
max. after 3000 hours,
at the latest after 6
months
For RD 0300 A:
max. after 2400 hours,
at the latest after 6
months
For RD 0360 A:
max. after 2000 hours,
at the latest after 6
months
• Contact Busch for an inspection.
If required, overhaul the machine.
Every 5 years
* Service interval for synthetic oil, shorten the interval when using mineral oil, contact
Busch Service
7.2 Oil Level Inspection
• Shut down the machine.
• When the machine is stopped, wait 1 minute before checking the oil level.
MAX
MIN
MAX
MIN
MAX
MIN
.