Figure : Minimum Installation Clearances To Combustible Materials (Inches)
A.
INSPECT SHIPMENT
carefully for any signs of
damage.
1. All equipment is carefully manufactured, inspected
and packed. Our responsibility ceases upon delivery
of crated boiler to the carrier in good condition.
2. Any claims for damage or shortage in shipment
must be filed immediately against the carrier by the
consignee. No claims for variances from, or shortage
in orders, will be allowed by the manufacturer
unless presented within sixty (60) days after receipt
of goods.
B.
LOCATE BOILER
in front of final position before
removing crate. See Figure 1.
1. LOCATE so that vent pipe connection to chimney
will be short and direct.
2. BOILER IS SUITABLE FOR INSTALLATION
ON COMBUSTIBLE FLOOR. Boiler cannot be
installed on carpeting.
3. FOR BASEMENT INSTALLATION, provide
a solid elevated base, such as concrete, if floor is
not level, or if water may be encountered on floor
around boiler.
4. PROVIDE RECOMMENDED SERVICE
CLEARANCE, if applicable, as follows:
a. Clearance from Jacket Front Panel -
•
24" for servicing burner
•
24" for flueway cleaning (MST288 &
MST396)
•
30" for flueway cleaning (MST513)
•
36" for flueway cleaning (MST629)
b. Clearance from Jacket Left Side Panel -
•
19" for burner swing door, if opened fully
with burner mounted, otherwise 1" with
burner removed
•
12" access clearance to service rear of
boiler if right side clearance is less
than 12"
• 1
" minimum if right side clearance is 12" or
larger to access and service rear of boiler.
c. Clearance from Jacket Right Side Panel -
•
6" minimum from external Electrical
Enclosure if left side clearance is 12" or
larger to access and service rear of the boiler
•
24" minimum from rear tankless heater (if
equipped) for servicing and removal of the
heater
d. Clearance from Jacket Rear Panel -
•
12" minimum for rear smokebox cleaning
(Note: This dimension will also be
controlled by horizontal to vertical to
horizontal smokepipe arrangement - See
Figures 2 and 15.)
5. For minimum clearances to combustible materials.
See Figure 2.
SECTION I: PRE-INSTALLATION
NOTES:
1. Listed clearances comply with American National Standard
ANSI/NFPA 31, Installation of Oil Burning Equipment.
2. MegaSteam™ boilers can be installed in rooms with
clearances from combustible material as listed above.
Listed clearances cannot be reduced for alcove or closet
installations.
3. For reduced clearances to combustible material, protection
must be provided as described in the above ANSI/NFPA 31
standard.
Содержание MST288
Страница 5: ... Figure 1 MST288 Thru MST629 Steam Boiler with and without Tankless Heater Beckett Burner Shown ...
Страница 11: ...11 Figure 4 Boiler Removal from Skid ...
Страница 19: ...19 Figure 9 Float Type LWCO and Pressure Limit Installation ...
Страница 25: ...25 Figure 12 Recommended Boiler Piping for Gravity Return Steam Boiler ...
Страница 34: ...34 Figure 18 Wiring Diagram Steam Hydrolevel CG450 Probe LWCO ...
Страница 35: ...35 Figure 18A Wiring Diagram Riello 40 Series Burner Steam Hydrolevel CG450 Probe LWCO ...
Страница 36: ...36 Figure 19 Wiring Diagram Steam McDonnell Miller PS 801 Probe LWCO ...
Страница 37: ...37 Figure 19A Wiring Diagram Riello 40 Series Burner Steam McDonnell Miller PS 801 Probe LWCO ...
Страница 38: ...38 Figure 20 Wiring Diagram Steam McDonnell Miller 67 Float LWCO ...
Страница 39: ...39 Figure 20A Wiring Diagram Riello 40 Series Burner Steam McDonnell Miller 67 Float LWCO ...
Страница 45: ...45 Figure 24 L1 and V1 Head Electrode Positioning and Gun Setting Beckett AFG ...
Страница 58: ...58 Bare Boiler Assembly ...
Страница 60: ...60 Jacket Assembly ...
Страница 62: ...62 MST288 Thru MST629 Steam Boilers Trim and Controls ...
Страница 64: ...64 Beckett AFG Burner ...