BULLDOG HEAT PUMP Vertical Stacked – Installation Manual
3
© Copyright 2017 CGC Group of Companies, Inc. Installation Manual is Subject to Change without Notice - Last Revised Aug 15, 2017
INSTALLATION
The information below details the installation procedure for a vertical stacked unit riser and cabinet.
Please read this document in its entirety prior to proceeding with the installation.
Specific site conditions may warrant variations in locations and dimensions.
GENERAL INSTALLATION CHECKLIST
1.
Remove packaging and inspect the unit. Carefully check for shipping damage or material
shortage; file a freight claim and notify appropriate sales representative if damage is found.
NOTE:
The chassis and front panel are shipped separately from the cabinet and risers.
2.
Verify the correct model and voltage as indicated by the model number.
3.
Verify the installation location of the unit using the sheet metal template that is provided.
4.
Verify that the power supply complies with the nameplate specification.