background image

2

For proper unit operation, check refrigerant charge using charging
information located on control box cover and/or in the Check

Charge section of this instruction.

IMPORTANT

: Maximum liquid--line size is 3/8--in. OD for all

residential applications including long line. Refer to Residential
Piping and Longline Guideline for further information.

IMPORTANT

: Always install the factory--supplied liquid--line

filter drier. If replacing the filter drier, refer to Product Data Digest
for appropriate part number. Obtain replacement filter driers from
your distributor or branch.

INSTALLATION

IMPORTANT

: Effective January 1, 2015, all split system and

packaged air conditioners must be installed pursuant to applicable
regional efficiency standards issued by the Department of Energy.

CUT HAZARD

Failure to follow this caution may result in personal injury.
Sheet metal parts may have sharp edges or burrs. Use care and

wear appropriate protective clothing and gloves when

handling parts.

CAUTION

!

Check Equipment and Job Site

UNPACK UNIT
Move to final location. Remove carton taking care not to damage

unit.

Inspect Equipment

File claim with shipping company prior to installation if shipment
is damaged or incomplete. Locate unit rating plate on unit corner

panel. It contains information needed to properly install unit.

Check rating plate to be sure unit matches job specifications.

Install on a Solid, Level Mounting Pad

If conditions or local codes require the unit be attached to pad, tie

down bolts should be used and fastened through knockouts
provided in unit base pan. Refer to unit mounting pattern in Fig. 2

to determine base pan size and knockout hole location.
For hurricane tie downs, contact local distributor for details and PE

(Professional Engineer) certification, if required by local

authorities.
On rooftop applications, mount on level platform or frame. Place

unit above a load--bearing wall and isolate unit and tubing set from
structure. Arrange supporting members to adequately support unit

and minimize transmission of vibration to building. Consult local

codes governing rooftop applications.
Roof mounted units exposed to winds may require wind baffles.

Consult the Application Guideline and Service Manual --
Residential Split System Air Conditioners and Heat Pumps for

wind baffle construction.

NOTE

: Unit must be level to within

2

_

(

3/8 in./ft ,.

9.5 mm/m)

per compressor manufacturer specifications.

Clearance Requirements

When installing, allow sufficient space for airflow clearance,

wiring, refrigerant piping, and service. Allow 24 in. (609.6 mm)
clearance to service end of unit and 48 in. (1219.2 mm) (above

unit. For proper airflow, a 6--in. (152.4 mm) clearance on 1 side of

unit and 12--in. (304.8 mm) on all remaining sides must be
maintained. Maintain a distance of 24 in. (609.6 mm) between

units or 18 in. (457.2 mm) if no overhang within 12 ft. (3.66 m)
Position so water, snow, or ice from roof or eaves cannot fall

directly on unit.

NOTE

:

18” (457.2 mm) clearance option described above is

approved for outdoor units with wire grille coil guard only.
Units with louver panels require 24” (609.6 mm) between units.

On rooftop applications, locate unit at least 6 in. (152.4 mm) above
roof surface.

Operating Ambient

The minimum outdoor operating ambient in cooling mode without

accessory is 55

_

F (12.78

_

C), and the maximum outdoor

operating ambient in cooling mode is 125

_

F (51.67

_

C).

Make Piping Connections

!

WARNING

PERSONAL INJURY AND ENVIRONMENTAL

HAZARD

Failure to follow this warning could result in personal injury or

death.
Relieve pressure and recover all refrigerant before system

repair or final unit disposal. Use all service ports and open all

flow--control devices, including solenoid valves.
Federal regulations require that you do not vent refrigerant to

the atmosphere. Recover during system repair or final unit

disposal.

CAUTION

!

UNIT DAMAGE HAZARD

Failure to follow this caution may result in equipment

damage or improper operation.
If ANY refrigerant tubing is buried, provide a 6--in (152.4

mm). vertical rise at service valve.

Refrigerant tubing

lengths up to 36--in (914.4 mm). may be buried without

further special consideration. Do not bury lines more than

36--in. (914.4 mm).

3/8---in. (9.53 mm) Dia.

Tiedown Knockouts in

Basepan(2) Places

View From Top

UNIT BASE PAN

Dimension in. (mm)

TIEDOWN KNOCKOUT LOCATIONS in. (mm)

A

B

C

23---1/2 X 23---1/2

(596.9 X 596.9)

7---13/16 (198.4)

4–7/16 (112.7)

18–1/16 (458.8)

26 X 26

(660.4 X 660.4)

9–1/8 (231.8)

4–7/16 (112.7)

21–1/4 (539.8)

31–1/2 X 31–1/2

(800.1 X 800.1)

9–1/8 (231.8)

6–9/16 (166.7) 24–11/16 (627.1)

35 X 35

(889 X 889)

9–1/8 (231.8)

6–9/16 (166.7)

28–7/16 (722.3)

A05177

Fig. 2 -- Tiedown Knockout Locations

Outdoor units may be connected to indoor section using accessory

tubing package or field--supplied refrigerant grade tubing of correct
size and condition. Rated tubing diameters shown in Table 1 are

recommended up to 80 ft. (24.38 m). See Product Data for

acceptable alternate vapor diameters and associated capacity losses.
For tubing requirements beyond 80 ft. (24.38 m), substantial

capacity and performance losses can occur. Following the
recommendations in the Longline Guideline will reduce these

losses. Refer to Table 1 for field tubing diameters. Refer to Table

 6

for accessory requirements.

Содержание 105A

Страница 1: ...CTRICAL SHOCK HAZARD Failure to follow this warning could result in personal injury or death Before installing modifying or servicing system main electrical disconnect switch must be in the OFF position There may be more than 1 disconnect switch Lock out and tag switch with a suitable warning label EXPLOSION HAZARD Failure to follow this warning could result in death serious personal injury and or...

Страница 2: ...rigerant piping and service Allow 24 in 609 6 mm clearance to service end of unit and 48 in 1219 2 mm above unit For proper airflow a 6 in 152 4 mm clearance on 1 side of unit and 12 in 304 8 mm on all remaining sides must be maintained Maintain a distance of 24 in 609 6 mm between units or 18 in 457 2 mm if no overhang within 12 ft 3 66 m Position so water snow or ice from roof or eaves cannot fa...

Страница 3: ...g Set lengths between 50 and 200 ft 15 2 and 61 0 m horizontal or 20 ft 6 1 m vertical differential 250 ft 76 2 m Total Equivalent Length refer to the Residential Piping and Longline Guide line Air Conditioners and Heat Pumps using Puron refrigerant 3 For alternate liquid line options on 18 42 size units see Product Data or Residential Piping and Application Guideline Install Liquid Line Filter Dr...

Страница 4: ...d line temperature is higher than indicated or reclaim refrigerant if temperature is lower Allow a tolerance of 3_F 1 7_C Units with Indoor Piston Units installed with indoor pistons require charging by the superheat method The following procedure is valid when indoor airflow is within 21 percent of its rated CFM 1 Operate unit a minimum of 15 minutes before checking charge 2 Measure suction press...

Страница 5: ... 32 88 31 86 30 84 29 82 28 317 94 34 92 33 90 32 88 31 86 30 84 29 326 96 36 94 34 92 33 90 32 88 31 86 30 335 98 37 96 36 94 34 92 33 90 32 88 31 345 100 38 98 37 96 36 94 34 92 33 90 32 364 104 40 102 39 100 38 98 37 96 36 94 34 374 106 41 104 40 102 39 100 38 98 37 96 36 384 108 42 106 41 104 40 102 39 100 38 98 37 395 110 43 108 42 106 41 104 40 102 39 100 38 406 112 44 110 43 108 42 106 41 1...

Страница 6: ...ing may occur Charge must be weighed in Note Superheat _F is at low side service port Allow a tolerance of 3_F 1 7_C Note Indoor dry bulb between 70_F and 80_F 21_C and 27_C Table 4 Required Suction Line Temperature SUPERHEAT TEMP _F SUCTION PRESSURE AT SERVICE PORT PSIG 107 8 112 2 116 8 121 2 126 130 8 138 8 140 8 145 8 0 35 37 39 41 43 45 47 49 51 2 37 39 41 43 45 47 49 51 53 4 39 41 43 45 47 4...

Страница 7: ...ds Use furnace transformer fan coil transformer or accessory transformer for control power 24v 40va minimum NOTE Use of available 24v accessories may exceed the minimum 40va power requirement Determine total transformer loading and increase the transformer capacity or split the load with an accessory transformer as required Final Wiring Check IMPORTANT Check factory wiring and field wire connectio...

Страница 8: ...arge will be needed for longer line sets charge unit to nameplate subcooling Unit Size 15 ft 4 57 m Line Set Charge lb kg 113A 114CNA 114CNC 105A 18 4 10 1 86 4 77 2 16 4 5 2 04 4 87 2 21 24 4 22 1 91 4 20 1 91 4 20 1 91 4 60 2 09 30 4 90 2 22 5 67 2 57 5 67 2 57 5 67 2 57 36 5 00 2 27 5 42 2 46 5 42 2 46 6 40 2 90 42 6 07 2 75 7 90 3 58 7 90 3 58 7 46 3 38 48 7 00 3 18 8 31 3 77 8 31 3 77 8 31 3 ...

Страница 9: ...trol Yes No No For tubing line sets between 50 and 200 ft 15 24 and 60 96 m and or 20 ft 6 10 m vertical differential refer to Residential Piping and Longline Guideline Additional requirement for Low Ambient Controller full modulation feature MotorMasterr Control 24 VAC HOT 24 VAC COM R C G W W1 Y Y2 R C C A C THERMOSTAT Typical FAN COIL AIR CONDITIONER G W2 HEAT STAGE 1 COOL STAGE 1 INDOOR FAN 24...

Страница 10: ...uction line filter driers in line longer than 72 hours S Do not install a suction line filter drier in liquid line S POE oils absorb moisture rapidly Do not expose oil to atmosphere S POE oils may cause damage to certain plastics and roofing materials S Wrap all filter driers and service valves with wet cloth when brazing S A factory approved liquid line filter drier is required on every unit S Do...