66/78 Commissioning
Bosch Rexroth AG, Control block SB24/34, RE 66170-B/2019-05-15
8.3.4 Air bleeding at EHR control valves
The hydraulic fluid flow via ports
P
and
R
must be applied.
1.
Close working port
A1
.
2.
Connect control valves with external return flow port
R1
to the tank.
3.
Apply a hydraulic fluid flow through the directional valve for at least 20 seconds
and alternatively actuate lifting solenoid at 50% (approx. 1.4 A) and the
lowering solenoid at 100% (max. 3.3 A).
8.4 Recommissioning after standstill
Recommissioning is necessary if the control block/control block segments
• have been decommissioned for more than 12 months
• have been disassembled
• have been repaired
• have been drained from hydraulic fluid or if hydraulic fluid was changed.
▶
For recommissioning, proceed as described in chapter 8.2 "Initial commissioning"
on page 63.