Bosch ESHCK Скачать руководство пользователя страница 5

Stainless Steel - Concentric Vent / Air Intake Kit Installation Manual | 10.2009                                                                  Technical specifications are subject to change without prior notice                         

 | 

5

 

Installation Manual

2  Installation

1.    Ensure all items listed in Section 1.1 are complete.

2.    Common installation practice is to determine the 

termination  and  exterior  wall  penetration  point  first. 
Next,  design  the  venting/intake  piping  layout  back  to 
the heater.   Keep in mind, centrally locating the water 
heater, whenever possible, is recommended to keep hot 
water distribution times even thoughout the structure.

3.     To determine the appropriate penetration point, refer to 

the allowable termination clearances listed in Figure 7.

4.    Once penetration point is determined, use a 5" hole saw 

with proper blade (depending on wall construction) to 

cut hole for kit installation.

5.    Insert Item 2 (Fig. 1) through exterior wall from the 

outside until flange is flush with wall surface.  Ensure 
that combustion air openings on Item 2 face toward the 
ground as shown in Fig. 6.  Secure flange to exterior wall 
with screws provided.

6.     Connect item 1 to item 2 (Fig. 1) from inside the 

structure. The air intake connection opening (Item 1) 
can be turned to best suit the connection of the intake 
pipe.  Secure both items with machine screws provided.  

7.    Locate end clamps on concentric kit (Fig. 3, step 1).  

Open clamps as shown in Figure 3, step 2.

Concentric Kit End

Exhaust 

vent pipe

Step 1

Step 2

Fig. 3     Concentric end clamps

8.    Insert vent piping through the concentric vent kit. Close 

end clamps around vent pipe (Fig. 4, step 3).  Secure 
clamps by inserting screws where shown (Fig. 4, step 4).

Concentric Kit End

Exhaust 

vent pipe

Step 3

Step 4

Exhaust 

vent pipe

Fig. 4     Securing vent piping with clamps

9.     On the outside of the structure, connect tee terminal to 

exhaust  vent  pipe  (Fig.  5).    Be  sure  to  maintain  12" 
clearance from exterior wall to tee terminal as indicated 
in Figure 6.

3" sealed stainless steel 

(AL29-4C) exhaust pipe

Concentric vent kit

Approved tee 

terminal

Air intake 

connection

Fig. 5 

Concentric vent assembly

10.  Connect combustion air piping to air intake connection 

on  concentric  vent  kit  (Fig.  5).  Secure  with  machine 

screws. 

Содержание ESHCK

Страница 1: ...Installation manual Concentric Vent Air Intake Kit Stainless Steel For Bosch Models GWH 715 ES GWH 2400 ES GWH 2700 ES Evolution 500 Part Number ESHCK ...

Страница 2: ...2 Installation Manual Stainless Steel Concentric Vent Air Intake Kit Installation Manual 10 2009 Technical specifications are subject to change without prior notice ...

Страница 3: ...stallation Manual 10 2009 Technical specifications are subject to change without prior notice 3 Installation Manual Table of Contents 1 Introduction 4 1 1 Items included with Concentric vent kit 4 1 2 Venting material compatibility 4 2 Installation 5 ...

Страница 4: ...eaters GWH 2400 ES GWH 2700 ES GWH 715 ES Evolution 500 1 1 Items included with Concentric Vent kit See Figure 1 Fig 1 Concentric vent kit components Item 1 Item 2 Item 3 Item 1 intake pipe connector Item 2 exterior wall chase Item 3 bag of screws This kit can be ordered from your local supplier part ESHCK 1 2 Venting material compatibility The exhaust vent piping used with this kit must be 3 seal...

Страница 5: ...ard the ground as shown in Fig 6 Secure flange to exterior wall with screws provided 6 Connect item 1 to item 2 Fig 1 from inside the structure The air intake connection opening Item 1 can be turned to best suit the connection of the intake pipe Secure both items with machine screws provided 7 Locate end clamps on concentric kit Fig 3 step 1 Open clamps as shown in Figure 3 step 2 Concentric Kit E...

Страница 6: ...ect to change without prior notice 10 Finish exhaust vent and combustion air piping installation back to the water heater 11 Complete tankless water heater installation per the water heater s installation manual Fig 6 12 Combustion air pipe Exhaust vent pipe Combustion air openings Fig 6 Completed concentric vent kit installation ...

Страница 7: ...o outside corner G Clearance to inside corner H Clearance to each side of center line extended above meter regulator assembly 36 in within a height 15 feet above meter regulator assembly I Clearance to service regulator vent outlet 36 in J Clearance to non mechanical air supply inlet to building or the combustion air inlet to any other application n i 2 1 n i 6 3 K Clearance to mechanical air supp...

Страница 8: ...rth Avenue Londonderry NH 03053 Tel 800 642 3111 Fax 603 584 1681 www boschhotwater com Bosch Thermotechnology Corporation reserves the right to make changes without notice due to continuing engineering and technological advances BTC 710003302 A ...

Отзывы: