3. MOUNTING INSTALLATION 

 

3.1 

CEILING MOUNTING 

 

IMPORTANT!

 Ensure that the ceiling is capable of taking the weight of the heater. 

For optimum results do not fit in ceilings higher than 3m. Air is taken in through the large grille and discharged through the smaller grille. The air intake 
and discharge areas must be kept completely clear for a minimum of 1.5m from the front of the heater. In an area using multiple units, heaters should 
be spread to provide an even heat distribution. 
Take out the internal heater by removing the end plate (disconnect the earth cable carefully) then remove the 10 screws on the front face and slide 
out the heater assembly remembering which way around it goes. There are 20mm electrical knockouts on the side of the case and the removable 
cover these might influence which way around you mount the case for easy neat wiring. Remember to leave plenty of clearance to allow the inner 
heater assembly to be inserted inside the main case after installation. 

 

 

 

Using the drawing above mark out the holes required to secure the heater case to the ceiling.  Use the 4 x keyhole slots and an additional 2 holes 
once installed to lock the heater in place. These addition 2 holes must be used to stop the possibility of the case sliding off its fixings. 

Secure to the ceiling using suitable fixings (not supplied). Depending on how you mount the heater case it may be easier to do some of the electrical 
connections before sliding the heater fully back into it. 

 

3.2 

DROP ROD MOUNTING 

The heater has 4 x M8 threaded holes suitable for using M8 drop rod studding. Fully screw the studding into each hole and use a lock nut to stop it 
rotating and coming out. Use the diagram above to determine the spacing of the drop rods. If you use drop rods you should be able to gain access to 
all the electrical connections without having to open the end cover of the heater. 

 
 

 

Содержание SMH-R30S

Страница 1: ...boxes due to supplies being taken from different phases 1 2 GENERAL SAFETY INSTRUCTIONS Remove all packaging and store it away from children check the package and heater for visible damage or tampering Familiarise yourself with the applications and limitations of the heater Ensure the heater is in good order and condition both physically and electrically before use If in any doubt do not use the u...

Страница 2: ... easy neat wiring Remember to leave plenty of clearance to allow the inner heater assembly to be inserted inside the main case after installation Using the drawing above mark out the holes required to secure the heater case to the ceiling Use the 4 x keyhole slots and an additional 2 holes once installed to lock the heater in place These addition 2 holes must be used to stop the possibility of the...

Страница 3: ...electrician before continuing Drawings show connections inside the 2 Terminal boxes on the top of the Slave heaters Do NOT use power tools to undo or do up terminal screws Please Note Specified cable sizes are for typical installations correction factors may need to be used when determining actual cable sizes Cable Sizes Mains Cable Use 1 5mm 3 Core Mains Cable see note above Additional Slave heat...

Страница 4: ...er fails to operate or the safety cut out operates again turn off the heater and contact a qualified electrician NOTE It is our policy to continually improve products and as such we reserve the right to alter data specifications and component parts without prior notice IMPORTANT No liability is accepted for incorrect use of this product WARRANTY Your BN Thermic product is guaranteed for one year f...