- 11 -
For installations where debris is approximately greater than
1/8” (3 mm) in size are present in
water, install a screen on the intake of the suction pipe to ensure that large solids do not pass
through the BLOOM. Verify that the intake screen is rated for the flow liquid capacity of your
BLOOM
and does not restrict the generator’s design liquid flow rate.
Discharge Piping Installation
Locate and install the discharge pipe following the recommendations detailed in Figure 3 for the
installation. Use pipe fittings as necessary to route the discharge piping from the BLOOM
unit to the tank wall. The discharge pipe can be routed over the top of or through the tank wall.
Install discharge pipe at the maximum water submergence depth and connect a 90
–
degree elbow to the end. Angle the discharge tangential to the tank to create a circular current
to assist with mixing.
Figure 7.
– BLOOM Discharge Pipe at Maximum Water Submergence Depth.