Zero Clearance 

Installation Instructions 

 
 
 

IS 500 LE / IS 800 LE Models 

 

 

 
 
 
 
 
 
 
 

 

 

 

Pecan Engineering Pty Ltd 

13 Acorn Road 

Dry Creek 

South Australia 5094 

Email [email protected] 

Phone: (08) 8349 8332 

Fax: (08) 8260 6643 

 
 
 

Содержание IS 500 LE

Страница 1: ... Zero Clearance Installation Instructions IS 500 LE IS 800 LE Models Pecan Engineering Pty Ltd 13 Acorn Road Dry Creek South Australia 5094 Email info pecan eng com au Phone 08 8349 8332 Fax 08 8260 6643 ...

Страница 2: ...ED 4 INSTALLATION INFORMATION 4 INSTALLATION CHECKLIST 4 INSTALLATION IN DETAIL 5 DIMENSIONS 5 CLEARANCE TO COMBUSTIBLE MATERIALS 6 FLOOR PROTECTOR HEARTH 7 VENTILATION 7 CLADDING 8 POWER SUPPLY FOR FAN 9 FLUE REQUIREMENTS 9 SUGGESTED FRAMING 10 ...

Страница 3: ...ND THE APPROPRIATE REQUIREMENTS OF THE RELEVANT BUILDING CODE OR CODES WARNING APPLIANCES INSTALLED IN ACCORDANCE WITH THIS STANDARD SHALL COMPLY WITH THE REQUIREMENTS OF AS NZS 4012 AS NZS 4013 WHERE REQUIRED BY THE REGUALTORY AUTHORITY I E THE APPLIANCE SHALL BE IDENTIFIABLE BY A COMPLIANCE PLATE WITH THE MARKING TESTED TO AS NZS 4012 AS NZS 4013 ANY MODIFICATION OF THE APPLIANCE THAT HAS NOT BE...

Страница 4: ...kit AS 2918 Additional double casings i e 200mm and 250mm diameter casings to extend from the top of the zero clearance box to the standard flue kit casings at the ceiling penetration Clearance between outer casing and ceiling minimum of 25mm e g 300mm hole in ceiling Floor Requirements if floor is heat sensitive If base of heater is a 250mm or more above the floor floor protector must be minimum ...

Страница 5: ...stible material such as masonry or Hebel blocks or may be constructed of timber and steel framing and clad with plaster board and fibre cement sheet Installation must comply with the standard AS NZS 2918 2001 Domestic Solid Fuel Burning Appliances Installation DIMENSIONS IS500LE Zero Clearance Box Outer Box Dimensions IS800LE Zero Clearance Box Outer Box Dimensions ...

Страница 6: ...n the enclosure 1 175mm 200mm Ceiling clearance 2 1100mm 1100mm Note Plaster board cladding over a timber frame is classed as a combustible surface 1 Clearance above within the enclosure minimum clearance from the top of the zero clearance box to any combustible material above 2 Ceiling clearance distance from top of zero clearance box to the ceiling cannot be less than the minimum clearance speci...

Страница 7: ...otector are dependent on the height above the floor at which the heater is installed Height above floor IS 500 LE IS 800 LE Width Depth in front of door opening Thickness Width Depth in front of door opening Thickness Ground level 900 450 22 5 1000 600 22 5 Less than 250mm 900 450 22 5 1000 600 22 5 250mm or more 900 300 6 1000 300 6 Note These dimensions do not include the floor protector continu...

Страница 8: ...lly no less than 180mm either side of the zero clearance box Important the bottom edge of the facia surround of the IS500LE and IS800LE finishes 5mm below the inside bottom surface of the zero clearance box After fitting the zero clearance box into the framing may choose to screw it down so doesn t move thereafter and the hole in the front cladding is being cut ensure that the bottom edge of the o...

Страница 9: ... as through a removable vent then ensure an extension cord long enough to reach out of the front of the opening is lying in the base of the cavity When connecting the lead from the fan to the extension cord it is suggested to tape the connection in the event that if the fan may require removal and the lead has to be pulled through the 50x50mm notch FLUE REQUIREMENTS Install a 150mm diameter double...

Страница 10: ... wall and standard Gyprock or equivalent can be used on the side walls Vents have been positioned top and bottom on both side walls This construction complies with the minimum clearance requirements The height of the heater above the floor and or the width of the enclosure may be varied as long as it meets the minimum clearances to combustible materials as detailed previously Note Additional suppo...

Страница 11: ...11 ...