TECHNICAL MAINTENANCE

Prior to performing any technical maintenance and repair disconnect the fan from the electric mains and wait until its rotating parts 
come to a complete stop.

While performing technical maintenance:
•  Check the grounding screw terminals and electric connectors for proper tightness and tighten them up if necessary.
•  Check the casing fastening screws for tightness and tighten them up if necessary.
•  Check the bolt connecting the motor shaft to the hub for proper tightness and tighten it up if necessary.
•  Check the fan impeller for contamination and clean it up if necessary. To clean the impeller, remove the side cover.
Technical maintenance must be carried out at least once a year.

DISCONNECT THE UNIT FROM POWER SUPPLY BEFORE 

ANY MAINTENANCE OPERATIONS!

AVOID LIQUID SPILLS ON THE MOTOR! DO NOT USE AGGRESSIVE SOLVENTS AND 

SHARP OBJECTS FOR CLEANING!

PRIOR TO COMMENCING ANY TECHNICAL MAINTENANCE PUT UP A PROHIBITORY 

SIGN ON THE FAN STARTING PANEL: 

“DO NOT SWITCH ON! MEN AT WORK!”

POSSIBLE MALFUNCTIONS AND THEIR ELIMINATION

Problem

Possible reasons

Elimination

The fan will not start.

No power supply.

Check the mains switch. Check the electrical connections 

against the wiring diagram. 

Jammed motor.

Carefully check the fan impeller for possible seizure and 

eliminate it, if necessary. If the impeller is in order, replace 

the electric motor. 

The switching equipment 

activates upon fan start-up.

Short circuit in the fan or the electric circuit between 

the fan and the switching equipment.

Eliminate the cause of a short circuit. 

Excessive current consumption due to an overload in 

the electric mains.

Eliminate the cause of excessive current consumption. 

Improper fan starting method. 

Use a soft starter or frequency converter to start the motor 

(see "Asynchronous Electric Motor Starting Methods" 

in the "Connection to power mains" section)

Improper switching equipment.

Re-select the switching equipment in accordance with the 

current regulations and equipment specifications. 

The installed switching equipment is of poor quality 

or its actual performance falls short of the rated values 

stated by the manufacturer.

Re-select the switching equipment by choosing a unit 

which successfully passed commutation and load tests 

and has a technical compliance certificate. The selection 

should be limited to the top five foreign switching 

equipment manufacturers. 

www.blaubergventilatoren.de

Axis-p

14

Содержание AXIS-P Series

Страница 1: ...Axial pressurisation fan USER S MANUAL EN Axis P...

Страница 2: ...ny reserves the right to modify the technical characteristics design or configuration of its products at any time in order to incorporate the latest technological developments No part of this publicat...

Страница 3: ...ing the unit control the user s manual must be turned over to the receiving operator UNIT INSTALLATION AND OPERATION SAFETY PRECAUTIONS Disconnect the unit from power mains prior to any installation o...

Страница 4: ...power mains prior to any technical maintenance Do not store any explosive or highly flammable substances in close proximity to the unit When the unit generates unusual sounds odour or emits smoke disc...

Страница 5: ...stems with high air flow rates THE UNIT SHOULD NOT BE OPERATED BY CHILDREN OR PERSONS WITH REDUCED PHYSICAL MENTAL OR SENSORY CAPACITIES OR THOSE WITHOUT THE APPROPRIATE TRAINING THE UNIT MUST BE INST...

Страница 6: ...60 40 C T tropical climate 10 50 C M maritime moderately cold climate 40 40 C O general climatic modification except maritime climate 60 50 C OM general maritime climatic modification 40 40 C V unive...

Страница 7: ...al box Casing modification with a terminal box d n holes d n holes MODEL DIMENSIONS MM L D D1 D2 d n B Axis P400 350 450 400 450 490 8 12 480 Axis P450 350 450 550 450 500 540 8 12 525 Axis P500 350 4...

Страница 8: ...quare cage rotor installed inside the casing The fan casing modifications depend on the electrical cable connection options The cable is connected to the electric motor terminal box via a cable gland...

Страница 9: ...The length of the straight duct section downstream of the fan must be 1 5 2 D Installation of shorter air ducts may result in insufficient air pressure and air flow The flexible joints EVAF AF are re...

Страница 10: ...crement Installation of a downstream contractor is not recommended Installation near bends To install the fan directly downstream of a bend elbow use a curved section with a large bending radius or an...

Страница 11: ...on The fan must be integrated into a ventilation or smoke extraction system with an automatic control system The fan motor is rated for connection to 400 V 50 60 Hz three phase alternating current Con...

Страница 12: ...smooth out the inrush the high startup torque has no adverse effects on the operation of the driven mechanism Soft start SS starting A soft starter gradually increases the voltage supplied to the moto...

Страница 13: ...ces of success The use of an FC in this case helps solve the problem fundamentally Standard switching equipment automatic circuit breakers contactors and motor starters is not designed to withstand pr...

Страница 14: ...rt No power supply Check the mains switch Check the electrical connections against the wiring diagram Jammed motor Carefully check the fan impeller for possible seizure and eliminate it if necessary I...

Страница 15: ...place the fan with a unit of proper standard size The fan supplies less air than expected Wrong calculation of the ventilation network and wrong selection of the fan Re calculate the network parameter...

Страница 16: ...handling requirements applicable for the particular type of cargo The unit can be carried in the original packaging by any mode of transport provided proper protection against precipitation and mecha...

Страница 17: ...nded use by the user within the guaranteed period of operation The faults are eliminated by means of replacement or repair of the unit components or a specific part of such unit component The warranty...

Страница 18: ...www blaubergventilatoren de Axis P 18...