Commissioning Instructions

• 

Leak testing should be carried out in accordance with the current Refrigeration Code of Good 

Practice*.

• 

Following leak testing, the system should be evacuated using accepted refrigeration practices. The 

vacuum pump should be connected to both the high and low pressure sides of the system with all shut-

off valves open.

• 

Refrigerant charging should be carried out in accordance with the current Refrigeration Code of Good 

Practice*.

• 

Extreme care should be taken to avoid direct contact with liquid refrigerant (freeze burns).

• 

Ensure the electrical wiring is in accordance with local  electrical  regulations  and  ensure  fan motor 

direction is correct.

8. 

Maintenance Instructions

• 

Buffalo Trident condensers require low maintenance apart from regular cleaning of the fin face. 

Frequency is dependent upon the operating environment of the condenser.

• 

It is recommended that fin surfaces are cleaned using a soft bristle brush and/or low pressure water, 

taking care to avoid all electrical components (electrical power must be isolated prior to cleaning).

• 

All fan motors contain bearings and are maintenance free.

9. 

De-commissioning Instructions

• 

Pump down refrigeration system into the receiver or suitable container. (As per Refrigeration Code of 

Good Practice *)

• 

Isolate power and remove electrical wiring (remove earth wire last) and associated components where 

necessary.

• 

Disconnect refrigeration piping and seal both the system and condenser connections (ensure that 

positive/negative pressure does not exist in condenser prior to disconnection).

• 

Condenser can now be removed from location (the use of lifting devices during removal is 

recommended where applicable).

* Code of Good Practice produced in conjunction with AFCAM.

10. Manufacturer

Our products are manufactured in compliance with applicable international standards and regulations. If you have 

any questions about how to use our products or if you are planning special applications please contact:

BITZER Australia Pty Ltd

Buffalo Trident Division 

25 Strzelecki Avenue

Sunshine VIC 3020, Australia

Tel.: +61 (0)3 8326 8200

Fax: +61 (0)3 9310 2520

[email protected]

www.bitzer.com.au

11. 

Service Address 

For local support please refer to our website www.bitzer.com.au for your nearest branch office.

Содержание BDC 152 (2F) (V)

Страница 1: ...ctrical power is to be isolated prior to the commencement of any electrical work During normal operation Pressurised Refrigerant is contained within the condenser Extreme care should be taken to avoid...

Страница 2: ...rate Using an appropriate lifting device refer Figure 1 for recommended lifting methods attach the legs to the condenser using the bolt kit supplied Place the condenser into the installation position...

Страница 3: ...ARE IN mm UNLESS OTHERWISE SPECIFIED DRAWING STANDARD AS1100 BDC 5F 6R V MAIN ASSY WITH SPREADER T CAVANAGH 23 8 17 REFER BOM 4500 22 60 M IN LE N G T H 6 0 M A X SPREADER BAR DISCHARGE LINE CONNECTI...

Страница 4: ...ission of BITZER Australia DATE DRAWN BY BDC 5F 6R H MAIN ASSY WITH SPREADER 1 20 A3 SHT 3 of 3 BITZER AUSTRALIA Pty Ltd A B N 70 057 670 023 3rd ANGLE PROJECTION DATE APPROVED BY INSPECTION DIMENSION...

Страница 5: ...Model s Dimensions in mm BDC 152 2F BDC 228 3F BDC 304 4F BDC 380 5F BDC 456 6F BDC 608 8F BDC 760 10F A 970 1250 1390 1680 1390 1810 2080 B 1110 1390 1530 1680 1530 1940 2220 C 1250 1530 1810 2140 18...

Страница 6: ...on with solid air restriction to 1 side of platform For a multiple condenser Installation with solid air restriction to 1 side of 1 end of platform For an individual condenser Installation with solid...

Страница 7: ...LATION T CAVANAGH 01 08 17 REFER BOM Figure 2 1 Part 2 2 Maximum height of solid air restriction from condenser platform is 2 8m Avoid obstructions within 2 x Diameter of fan above condenser For alter...

Страница 8: ...0 023 3rd ANGLE PROJECTION DATE APPROVED BY INSPECTION DIMENSIONS XXXXX DECIMAL 1 0mm ONE DECIMAL 0 5mm TWO DECIMAL 0 2mm ANGLE 0 5 U N O TOLERANCES MASS kg MATERIAL FINISH NAME DO NOT SCALE ALL DIMEN...

Страница 9: ...rical power must be isolated prior to cleaning All fan motors contain bearings and are maintenance free 9 De commissioning Instructions Pump down refrigeration system into the receiver or suitable con...

Страница 10: ...Zealand BITZER Australia Pty Ltd Unit 5 5 7 Henry Rose Place Albany 0632 Auckland New Zealand tel 64 9 415 2030 www bitzer com au In the interest of continuous improvement BITZER reserves the right to...

Отзывы: