S19 Pro Server Installation Guide 

Environmental Requirements 

Please run your server in accordance with the following requirements

 

1. Basic Environmental Requirements:

1.1.

 

Climatic Conditions: 

Description 

Requirement 

Operating Temperature 

0-40

Operating Humidity 

10-90%RH (non-condensing)

Storage Temperature 

-20-70

Storage Humidity 

5-95%RH

non-condensing

Altitude

 

<2000m 

1.2. Site Requirements of the Server Running Room: 

Please keep the server running room away from industrial pollution sources: 

For heavy pollution sources such as smelters and coal mines, the distance should be more than 5km. 

For moderate pollution sources such as chemical industries, rubber and electroplating industries, the distance should be more than 

3.7km. 

For light pollution sources such as food factories and leather processing factories, the distance should be more than 2km. 

If unavoidable,

 

the site should be chosen in the perennial upwind direction of the pollution source.   

Please do not set your location within 3.7km from the seaside or the salt lake. If unavoidable, it should be built as airtight as 

possible, equipped with air conditioning for cooling. 

1.3. Electromagnetic Environmental Conditions: 

Please keep your site away from transformers, high-voltage cables, transmission lines and high-current equipment, for example, 

there should be no high-power AC transformers (>10KA) within 20 meters, and no high-voltage power lines within 50 meters. 

Please keep your site away from high-power radio transmitters, for example, there should be no high-power radio transmitters 

(>1500W) within 100 meters. 

2. Other Environmental Requirements

The server running room shall be free of explosive, conductive,magnetically conductive and corrosive dust. The requirements of 

mechanical active substances are shown below:

 

2.1 Requirements of Mechanical Active Substances 

Mechanical Active Substance 

Requirement 

Sand

 

<= 30mg/m

3

 

Dust (suspended) 

<= 0.2mg/m

3

 

Dust (deposited)

 

<=1.5mg/m

2

Содержание ANTMINER 19 Series

Страница 1: ...ications using Bitmain components To minimize the risks associated with customer products and applications customers should provide adequate design and operating safeguards Bitmain does not warrant or represent that any license either express or implied is granted under any Bitmain patent right copyright or other Bitmain intellectual property right relating to any combination machine or process in...

Страница 2: ...n of Bitmain Information in this document is subject to change without notice and does not represent a commitment on the part of Bitmain Although the information in this document has been carefully reviewed Bitmain does not warrant it to be free of errors or omissions Bitmain reserves the right to make corrections updates revisions or changes to the information in this document Bitmaintech Pte Ltd...

Страница 3: ...Specifications 7 2 Setting Up the Server 9 3 Configuring the Server 10 4 Monitoring Your Server 13 5 Administering Your Server 14 5 1 Checking Your Firmware Version 14 5 2 Upgrading Your System 14 5 3 Modifying Your Password 15 5 4 Restoring Initial Settings 15 Environmental Requirements 16 Regulations 18 ...

Страница 4: ... Back View Caution 1 The equipment must be connected to an earthed mains socket outlet The socket outlet shall be installed near the equipment and shall be easily accessible 2 The equipment has two power inputs only by connecting those two power supply sockets simultaneously can the equipment run When the equipment is powered off be sure to power off all power inputs 3 DO NOT remove any screws and...

Страница 5: ... 5 S19 Pro Server Installation Guide 1 Overview 1 1 S19 Pro Server Components The main components and controller front panel of S19 Pro servers are shown in the following figure ...

Страница 6: ...Server Installation Guide 1 Overview APW12 Power Supply Note 1 Power supply APW12 is part of S19 Pro server For detailed parameters please refer to the specifications below 2 Additional two power cords are needed ...

Страница 7: ...29 5 5 Detailed Characteristics Value Power Supply Power supply AC Input voltage Volt 1 1 200 240 Power supply AC Input Frequency Range Hz 47 63 Power supply AC Input current Amp 1 2 20 1 3 Hardware Configuration Networking connection mode RJ45 Ethernet 10 100M Server Size Length Width Height w o package mm 2 1 370 195 5 290 Server Size Length Width Height with package mm 570 316 430 Net weight kg...

Страница 8: ... has been disabled 2 If the user fails to use the product in accordance with the given instructions specifications and conditions provided or change the function setting without Bitmain s prior consent Bitmain will not be liable for any damage arising therefrom 1 1 Caution Wrong input voltage may probably cause server damaged 1 2 Max condition temperature 40 C altitude 0m 1 3 Two AC input wires 10...

Страница 9: ...d the following file IPReporter zip 3 Extract the file 4 Right click IPReporter exe and run it as Administrator 5 Select one of the following options Shelf Step Position suitable for farm servers to mark the location of the servers Default suitable for home servers 6 Click Start The file IPReporter zip is supported by Microsoft Windows only The default DHCP network protocol distributes IP addresse...

Страница 10: ...ndow on your computer screen 7 In your web browser enter the IP address provided 8 Proceed to login using root for both the username and password 9 In the Protocol section you can assign a Static IP address optional 10 Enter the IP address Subnet mask gateway and DNS Server 11 Click Save 12 Click https support bitmain com hc en us articles 360018950053 to learn more about gateway and DNS Server ...

Страница 11: ... 11 S19 Pro Server Installation Guide 2 Setting Up the server ...

Страница 12: ... and Sleep mode The server enters the sleep mode under the condition that the control board is powered while hashboards are not powered 2 Set the options according to the following table Option Description Mining address Enter the address of your desired pool The S19 servers can be set up with three mining pools with decreasing priority from the first pool pool 1 to the third pool pool 3 The pools...

Страница 13: ...p shown on the bottom of kernel log page Meanwhile the server temperature on the dashboard interface turns to abnormal and shows Temp is too high 2 Monitor your server according to the descriptions in the following table Option Description Number of chips Number of chips detected in the chain Frequency ASIC frequency setting Real Hashrate Real time Hashrate of each hash board GH s Inlet Temp Tempe...

Страница 14: ...on on the bottom 2 Firmware Version displays the date of the firmware your server uses In the examples below the server is using firmware version 20200405 5 2 Upgrading Your System Make sure that the S19 Pro server remains powered during the upgrade process If power fails before the upgrade is completed you will need to return it to Bitmain for repair To upgrade the server s firmware 1 In System c...

Страница 15: ...t the server and it will turn to the setting page 5 3 Modifying Your Password To change your login password 1 In System click the Password tab 2 Set your new password then click Save 5 4 Restoring Initial Settings To restore your initial settings 1 Turn on the server and let it run for 5 minutes 2 On the controller front panel press and hold the Reset button for 10 seconds Resetting your server wi...

Страница 16: ...able the site should be chosen in the perennial upwind direction of the pollution source Please do not set your location within 3 7km from the seaside or the salt lake If unavoidable it should be built as airtight as possible equipped with air conditioning for cooling 1 3 Electromagnetic Environmental Conditions Please keep your site away from transformers high voltage cables transmission lines an...

Страница 17: ...uirements of Corrosive Gas Corrosive Gas Unit Concentration H2S ppb 3 SO2 ppb 10 Cl2 ppb 1 NO2 ppb 50 HF ppb 1 NH3 ppb 500 O3 ppb 2 Note ppb part per billion refers to the unit of concentration 1ppb stands for the volume ratio of part per billion ...

Страница 18: ...rence in which case the user will be required to correct the interference at his own expense EU WEEE Disposal of Waste Equipment by Users in Private Household in the European Union This symbol on the product or on its packaging indicates that this product must not be disposed of with your other household waste Instead it is your responsibility to dispose of your waste equipment by handling it over...

Отзывы: