6. Insert
each
Backstay
(H) into the welded attachment tubes located on the
90
°
Corner
(C) and the
Backstay
Brackets
(I). Install and tighten a
5/16” x 2 3/4” Hex Bolt
(M) and a
5/16” Nylon Lock Nut
(N) at each loca-
tion. Tighten the
Backstay Bracket
(I) hardware. See Figure 2 and 3.
7. Slide
the
Connecting Bar
(E) into the
Long Inner Tube
(G) through the channel so that at least 2 holes are
lined up. Slide the
Ground Sleeves
(G) into the bottom of the
Uprights
(B). Install two
3/8” x 1” Hex Bolts
(J) on each. The
Long Inner Tube
(G) should be protruding 23 1/2” below the
Upright
(B). See Figure 3.
8. Dig holes a minimum of 8” in diameter and at least 30” deep on the goal line. It is advisable to bell out the
bottom of the holes to improve goal stability. Make sure the goal is centered on the field before digging. The
front surface of the goal should be even with the front edge of the goal line when installed. The distance be-
tween the holes will be determined by the purchased goal size. The 24’ x 8’ goal requires the holes to be 24’4”
apart on center, the 21’ x 7’ goal requires the holes to be 21’4” apart on center, the 18 1/2’ x 6 1/2’ goal re-
quires the holes to be 18’10” apart on center, the 12’ x 6 1/2’ goal requires the holes to be 12’4” apart on cen-
ter, and the 9’ x 4 1/2’ goal requires the holes to be 9’4” apart on center.
9. Plan on having 2” x 4” wood bracing materials available prior to mixing the concrete to help insure that the
Uprights
(B) are plumb and the
Crossbar
(A) is level and at the correct height.
10. If you are not using
Optional SC44S Ground Sleeves
(F) proceed to instruction number 12.
11. When installing
Optional SC44S Ground Sleeves
(F) it is critical that the ground sleeves are precisely posi-
tioned in the concrete footing to insure easy installation and removal of the goal. For best results slide the
ground
Optional Ground Sleeves
(F) onto the complete assembled goal and temporarily attach with duct
tape to the
Upright
(B). Place the entire goal / ground sleeve assembly into the concrete footing using 2” x 4”
wood bracing to insure that everything is plumb, level, the correct height, and properly positioned to the field.
12. It will take approximately three to four 1/3 cubic feet bags of concrete for each hole depending on the actual
size you dig your holes. Please allow 7 days for the concrete to completely cure before removing wood
bracing.
13. To install the net position
Net Attachment Clips
(P) into the slots in each
Upright
(B), and
Crossbar
(A)
approximately 12” - 18” apart. The
Net Attachment Clips
(P) slip into the slot and twist 90° into position with
the opening to the outside of the goal. See Figure 3.
14. Using the
Net Ground Stakes
(O), evenly spaced, anchor the bottom of your net to the turf.
NOTE:
If using
Optional SC44S Ground Sleeves
(F) use cap to protect
Optional SC44S Ground Sleeves
(F) when goal is removed.