Step 16 Install Doors & Hardware

4.

Before fastening the hinges to the side trim,

temporarily prop the doors in the opening. Leave
a space at the top and bottom of the doors and
between the doors and the side trim to allow
room for the doors to expand due to humidity.

If your door opening is out of square, the space

around the doors will not be even. You can
remove and re-position the side trim to make
allowances for this. The side trim does not have
to be flush with the frame of the door opening.
You can move the trim in or out to make the
door spacing equal.

5.

Determine position of hinges and install to side

trim with 2" screws.

6.

Install door hasp on double doors. When properly

installed the hasp will fold in half to receive
locking latch and the screw heads will be
covered.

7.

Install a barrel bolt on the lower back of the door

to secure this door in place when closed. You
will need to drill a hole for the round shaft to
drop into.

8.

Install another barrel bolt at the top of the door.

Barrel Bolt on the

back of left door

Left Door

Siding Extends Past Trim

Fold Hasp to Cover

Screws

1.

Lay the left door with the trim facing up. The

siding on the left door extends past the door trim.
See detail below.

2.

Install 5" hinges to the left side of the door frame.

To position the hinge properly, hold the rectangular
plate against the frame. Use 1-1/4" black screws.

3.

Install hinges to the right side of the other door.

Remove Watermark

Wondershare

PDFelement

Содержание cypress 1016

Страница 1: ...22 This manual is copyrighted Under the copyright laws this manual may not be copied in whole or in part without consent from RBS Holdings LLC Copyright 2022 Manufactured by RBS Holdings LLC 205 Arlin...

Страница 2: ...to build your own or pour a cement pad Terminology Square Confirm corners are at 90 degrees Plumb Confirm walls and trusses are straight vertically Wall Plate Top and bottom 2x4s used to frame walls T...

Страница 3: ...to change For a concrete slab install sill sealer as a moisture barrier between the concrete and the wall plates Foam sill sealer can be purchased at home centers in rolls 3 1 2 or wider Material Desc...

Страница 4: ...for a total of 2 two gables 4 Select 2 two 62 long 2x4 boards with angled ends to make the first truss Secure the tops together with a 24 wide OSB gusset Turn truss over and install another 24 wide g...

Страница 5: ...Edge 60 Wall Plate Tongue Edge Cut Edge A B 3 Nail both wall frames together with 4 four 10d sinkers on each side 4 Square frame measure diagonally corner to corner The measurement should be 141 1 2 5...

Страница 6: ...other end wall frame 11 Square wall frame Select a 12 1 2 wide siding panel with a tongue edge Install this panel with the Cut edge flush with the end of the wall frame Install siding flush with the 2...

Страница 7: ...wall frame The measurement should be 138 1 2 Install 2 two full width siding panels Install the first siding panel with the LAP edge extending 3 1 2 past the end of the wall frame Install a full width...

Страница 8: ...l width siding panel The last siding panel will be installed after the walls are erected on the floor LAP Edge 6 Install 72 wall studs between the top and bottom plates 5 Position 2 two 68 1 2 long 2x...

Страница 9: ...4 Top Plate 19 3 4 24 69 1 2 Header Support 2 Install a 48 x 75 3 4 siding panel to the back wall Use 6d galv nails Nail along the adjoining siding panel Step 5A Set Walls 1 Secure the back wall betwe...

Страница 10: ...r Nail through studs with 10d sinkers 2x4 Wall Brace Step 5B Set Walls Continued 67 1 2 Door Header 64 1 2 Wall Plate 3 Install front wall frames between the end walls 4 Temporarily install 2 two 2x4...

Страница 11: ...3 Finish by installing a 36 long 2x4 4 Repeat to install tie plates on the front wall Step 6 Install Siding on Front Wall 1 Select a full with siding panel and install at the front left corner 2 Insta...

Страница 12: ...nside of the building and flush with 2x4s on end wall 2 Install a 10 to 12 long 2x4 block on the back wall using 10d sinkers Secure the truss to the 2x4 block with 2 two 10 sinkers Install 2x4 Block S...

Страница 13: ...g should extend no more than 1 2 above the 2x4 frame and 1 1 2 past gable ends 60 Long Z Flashing Roof Gable End Wall Siding Install 2 two 60 pieces of Z flashing across the top of the siding on the e...

Страница 14: ...48 long 2x4 next 3 Cut to fit a 72 long 2x4 to finish against gable 4 Repeat to install 2x4 on the back wall 1 Starting from left end wall install the first truss measuring 21 3 4 from the face of the...

Страница 15: ...ush with the siding on the other gable 4 Repeat to install 1x4 fascia on the back wall Step 12B Install Trusses Continued 1 Install 72 long 1x4 fascia trim over the 2x4 Truss Header on the front wall...

Страница 16: ...row of sheathing will be about 1 below the ridge to allow for optional ridge venting See detail below See supplier of shingles to purchase ridge venting Siding Roof Sheathing 2x4 Truss Header Straight...

Страница 17: ...y want to move the trim later when you install the doors 6 Install a 72 long 1x3 trim board centered across the top of the vertical trim 3 4 of siding will be revealed at top of door 2 Install 75 3 4...

Страница 18: ...ews 6 Install door hasp on double doors When properly installed the hasp will fold in half to receive locking latch and the screw heads will be covered 7 Install a barrel bolt on the lower back of the...

Страница 19: ...ards 6 2x4 48 Plate Boards 6 2x4 10 12 Blocks for Truss Jig 4 1x4 64 3 8 Gable Trim 4 1x4 77 1 4 Corner Trim 4 1x3 75 3 4 Corner Trim 3 1x3 72 Door Trim 2 1x4 74 Fascia Trim 2 1x4 72 Fascia Trim 2 1x4...

Отзывы: