COMMISSIONING AND MAINTENANCE

10

If copper piping has been used and joints have been 

hot brazed, flush out the system to remove any braz-

ing residues. Seal test the system after you have 

flushed it out.

The  solar  circuit  must  be  immediately  filled  with  a 

mixture of water and glycol, that avoids freezing and 

corrosion.

15  SYSTEM FILLING COCK

Before filling the system:

-  Cut power off to the solar station and to the connect-

ed integration system, by setting the system's main 

switch and the device's main switch to OFF

Always use a mixture of water and glycol suitable for 

solar applications. Choose the mixture according to 

the minimum temperature that can be reached at the 

installation site and to the maximum service tempera-

ture of solar collectors. For further information, please 

refer to the glycol safety data sheet.

When using glycol not pre-mixed:

-  Do NOT part fill the circuit with pure glycol then add 

water later.

-  Ensure that filling water characteristics comply with 

prevailing  regulations;  if  that  is  not  so,  filling  water 

must be treated. Use portable treatment systems, for 

instance. In particular, when chlorine content is very 

high (> 50ppm) you must use distilled water for the 

mixture.

VR

B

A

C

Mixture

of glycol

and water

PC

PC 

Heat transfer fluid filling pump

To fill the system, proceed as follows:

-  Verify the flow-meter (C) is completely open

-  Connect the filling pump (PC) as shown

-  Turn handle on valve (VR) clockwise

 

Open taps (A) and (B) on the return tube

-  Open manual degassing tap and any bleeder valve, 

located at the highest points of the system, and keep 

them open throughout the filling procedure.

-  Pump the heat transfer fluid around the circuit with an 

external filling pump until all air bubbles have been 

eliminated. Close the manual bleed valve and any 

vent valves opened previously.

-  Turn handle on valve (VR) counter clockwise

-  Temporarily raise the pressure in the system to 4 bar.

-  Start up the system for about 20 minutes.

-  Repeat air bleeding operation until system is com-

pletely free of air bubbles.

-  set the system pressure.

-  Close taps (A) and (B).

The set pressure must ensure that the one measured 

at the solar collectors is positive with respect to the 

ambient one (avoid depression in the solar field) and 

must be set considering both the safety valve open-

ing pressure (6) and the solar expansion reservoir 

pre-charge pressure. To set the system pressure cor-

rectly, refer to the design manual.

Do not fill the system in bright, sunny conditions or if 

the collectors are hot.

Use a manual bleed valve, which should be installed 

at the highest point in the system, to ensure that all air 

bubbles have been eliminated from the circuit.

Содержание 20116162

Страница 1: ...Installation Manual 1 2 3 4 5 0 6 Solar Solar station CONNECT SOLAR R 7 5m Installation Manual EN...

Страница 2: ...by a qualified heating engineer b This instruction manual is an integral part of the prod uct It must be kept safe and must ALWAYS accom pany the product even if it is sold to another owner or transfe...

Страница 3: ...sed a Do not dispose of packaging material into the envi ronment or leave it within the reach of children since it can become a potential hazard Dispose of packag ing material in compliance with appli...

Страница 4: ...ing 7 TECHNICAL SPECIFICATIONS DESCRIPTION Return solar station Maximum working pressure 6 bar Maximum operating temper ature 110 C Dimensions LxHxP 264x362x215 mm Net weight with insulation 3 8 kg Po...

Страница 5: ...ll safety and control devices and to permit easy maintenance 9 1 Recommended minimum distances Recommended distances for assembly and maintenance are 300 mm on each side including expansion tank Put t...

Страница 6: ...can be used seal fittings with high temperature sealant 180 C suitable for solar applications 12 PUMP CONTROLLER The circulator is produced with maximum hydraulic head configuration of 7 5 meter USER...

Страница 7: ...indicates the circulator performance or internal control possibility LEDs no 2 and 3 indicate different control mode possibility and LEDs no 4 and 5 indicate the curve type setting 1 2 3 or 4 These LE...

Страница 8: ...rs as shown in the figure PWM CONNEC TOR POWER SUP PLY To control the circulator in on off mode the PWM cable is not required To control the circulator in modulating mode by using a solar regulator ve...

Страница 9: ...iL 1 V Input signal current IiH 10 mA Input Duty cycle PWM 0 100 14 SYSTEM FLUSHING Before filling the system with mixture of water and glycol it is necessary to flush the pipes of the solar system to...

Страница 10: ...l and water PC PC Heat transfer fluid filling pump To fill the system proceed as follows Verify the flow meter C is completely open Connect the filling pump PC as shown Turn handle on valve VR clockwi...

Страница 11: ...the safety data sheet supplied with the glycol 17 2 Disassembling the circulator b Remove the circulator when system has cooled down Before removing circulator C Cut power off to the solar station and...

Страница 12: ...23 A 23900 Lecco LC www berettaboilers com The manufacturer strives to continuously improve all products Appearance dimensions technical specifications standard equipment and accessories are therefore...

Отзывы: