STEP 7
( Power Unit Installation )
1. Mount the power unit to the mounting bracket
using the 5/16” x 3/4” hex bolts and nylon nuts
then fill the reservoir with 15 quarts of 10-WT
hydraulic oil or Dexron III automatic transmission
fluid. ( See Fig. 11 )
STEP 8
( Routing Hydraulic Hoses )
1. Install the two 90 degree hydraulic fittings to the
POWER PORT and RETURN PORT of the power
unit and connect the hoses as described below. It
will be necessary to remove shipping plugs from
both ports prior to installing fittings.
2. Install the two standard bulkhead couplers at the
outside of the POWERSIDE RUNWAY adjacent to
the power unit. Tighten securely.
3. Install the two 90-degree fittings at the cylinder
ports. On the pipe thread side of the fittings it is
recommended to use teflon tape or pipe sealer. DO
NOT USE TEFLON TAPE on JIC flared end.
4. Connect hydraulic hoses as shown below making
sure to first pass through the retaining rings located on
the underside of the runway. MAKE SURE HOSES
ARE KEPT CLEAR OF CABLES. ( See Fig. 12 )
10
Fig. 11
Fig. 12