Split-type room air conditioner / Installation Manual
10.1 Before test run
Only perform test run after you have completed the following steps:
•
Electrical Safety Checks – Confirm that the unit’s electrical system is safe and operating properly
•
Gas Leak Checks – Check all flare nut connections and confirm that the system is not leaking
•
Confirm that gas and liquid (high and low pressure) valves are fully open
10.2 Test run instructions
You should perform the Test Run for at least 30 minutes.
1. Connect power to the unit.
2. Press the ON/OFF button on the remote controller to turn it on.
3. Press the MODE button to scroll through the following functions, one at a time:
•
COOL – Select lowest possible temperature
•
HEAT – Select highest possible temperature
4. Let each function run for 5 minutes, and perform the following checks:
List of checks to perform
Pass/Fail
No electrical leakage
Unit is properly grounded
All electrical terminals properly covered
Indoor and outdoor units are solidly installed
All pipe connection points do not leak
Outdoor (2):
Indoor (2):
Water drains properly from drain hose
All piping is properly insulated
Unit performs COOL function properly
Unit performs HEAT function properly
Indoor unit louvers rotate properly
Indoor unit responds to remote controller
10
Test run
Содержание BEVPI 090
Страница 118: ......
Страница 119: ......
Страница 120: ...www beko com ...
Страница 121: ...Air conditioner remote control User Manual EN ...
Страница 128: ...8 24 EN Air conditioner remote control User Manual 3 Handling the remote control ...
Страница 142: ......
Страница 143: ......
Страница 144: ...www beko com ...
Страница 145: ......
Страница 152: ...8 24 SI Pretvornik Klimatska Naprava Slika daljinskega Uporabniški priročnik 3 Ravnanje z daljinskim upravljalnikom ...
Страница 166: ......
Страница 167: ......
Страница 168: ...www beko com ...