6. Mounting sequence light lines 

1.

 

plant out the position of mounting brackets (see chapter 4) by means of a laser 

2.

 

drill the holes and mount the brackets 

3.

 

click  the BB Lightpipe into the bracket with 2 persons 

4.

 

lock the luminaires into the bracket by means of pop rivets 

5.

 

connect the trough-wiring and infeed cable (1) with the Plug & play connectors (3) 

6.

 

if necessary, adjust the phase selection 

7.

 

place the connectors (3) and sealing disc (2)  into the driver housing (4) 

8.

 

make sure the sealing disc properly closes the driver housing 

9.

 

slide the cover (5) over the open gap of the fixture to finish  

 

Picture: connecting a Start Cable (6091) 

 

Содержание E12E4

Страница 1: ...Lightpipe EVO Index Index 1 1 Introduction 2 2 Article numbering 3 3 Types 4 4 Mounting 5 5 Connection diagram light lines 6 6 Mounting order light lines 7 7 Through wiring the light line 8 8 Diagram...

Страница 2: ...ions such as parking garages tunnels train stations and much more By making use of durable materials in combination with the long lifetime of the electrical components a maintenance free long lasting...

Страница 3: ...ipe is pre wired wired or not end The through wiring consists of 3 fase N and Ground All BB Lightpipes have DALI trough wiring also the End type Number of LED modules The number of LED modules is rela...

Страница 4: ...P66 5000K 70 700mA Diffuse 3 phase Plug play E4E4 BB Lightpipe EVO End 4M bi IP66 5000K 70 700mA Diffuse 3 phase Plug play E6W2 BB Lightpipe EVO Wired 6M mono IP66 5000K 70 700mA Diffuse 3 phase Plug...

Страница 5: ...cket can be placed in any position on the base profile Fixture length Number of brackets Positie 2 to 4 meters 2 mounting brackets 0 5m from the end 6 meters 3 mounting brackets 0 5m from the end one...

Страница 6: ...ut prior notice 5 Connection diagram light lines The connection diagram below applies to the lengths 4 6 8 en 12 meter Wago 770 205 male Wago 770 215 female Fase selection Adjustment over the 3 phases...

Страница 7: ...k the BB Lightpipe into the bracket with 2 persons 4 lock the luminaires into the bracket by means of pop rivets 5 connect the trough wiring and infeed cable 1 with the Plug play connectors 3 6 if nec...

Страница 8: ...sealing disk closes the housing properly to ensure water resistance Picture 3 Slide the cover onto the transition of the two fixtures and fasten the torx screws LED module wiring In the 8 and 12 mete...

Страница 9: ...prior notice 8 Diagram for stand alone mounting The electric diagram below shows the connection of the 2 2 meter BB Lightpipe For the stand alone fixtures the installer needs to take care of the infe...

Страница 10: ...pe NICHIA High power ceramic LED circuit All LEDs in series LED protection NTC on LED main board Ambient temperature 40 50 C Colour value 5000 Kelvin standard 2700 6500 K optional All wires LSZH Low S...

Страница 11: ...res the pallets for transport are bigger than usual The maximum dimensions are 6 2m to 0 8m to 1 5m l x b x h and the pallets have a maximum weight of 1000kg In the factory the light emitting part of...

Страница 12: ...rent of the LED driver has to be taken into account when designing the electrical installation and determining fuse types The inrush current peak can cause the fuse to clog out when turning on multipl...

Отзывы: