Bardiani VVF Скачать руководство пользователя страница 3

prObLEM

pLANNED MAINTENANCE

VALVE SpECIFICATIONS:

- Max. working pressure :

10 bar (145 psi) DN15--100

8 bar (115 psi) DN125

6.5 bar (94 psi) DN150

- Min. working pressure :

Vacuum

-

 Max. product temperature :

 

120 °C (284 °F) 

- Min. product temperature :

-10 °C (14 °F) 

- Material in contact with the product :

 

AISI 316L (1.4404)

- Gasket in contact with the product (FDA homologation):

EPDM, FKM, MVQ(silicon), HNBR (other seals avaiable upon 

request).

- Finish on surfaces in contact with the product :

Ra 0.8 µm (other types of surface finish upon request).

HANDELING 

Based upon the weight of the valve it is necessary to use the appropriate carrying and restraining equipment (mobile 

crane, fork lift, pump truck, etc.)

INSTALLATION

The valve must be fitted to the installation in such a way as not to cause flexing or torsion loads due to the weight of the 

valve. It is advised to connect to the installation using tube work and materials at least consistent with the characteristics 

equal to the valve itself.

USE

The opening and closing of the valve must be done slowly in order to avoid shock waves /air locks in the installation in 

which the valve is fitted.

MAINTENANCE!

                      Make sure before carrying out any maintenance work that the installation to which the valves

                      are connected is isolated, and that there are no liquids remaining, and that the installation is not

                      pressurised.

The normal maintenance

 

consists of the replacement of the seals present within the valves.

PROBLEM

 POSSIBLE CAUSE

POSSIBLE REMEDY

 External leakage

 Worn out gasket

 Repalce gasket

Internal lekage with closed valve,                   

caused by normal wear

 External lekage

 Too high pressure 

 Repalce with gasket  of different

 elastomer type

 Too high temperature

 Internal with closed valve occuring                                                                                            

 earlier than normal wear

 Aggressive fluids

 Modfy opeation conditions

 Too many active control 

 Difficult opening 

 Incorrect elastomer type of gaskets

 Replace with gasket of different elastomer type

PLANNED MAINTENANCE

VALVE GASKETS

Preventive

 Replace after 12 months

  In case of leakage

 Replace at the end of the day

Periodical

 Check for correct operation and absence of 

 leakage

 Record all actions taken

SCrAppING AND DISpOSAL

For the scrapping of the valve proceed as follows:

-Disassemble all the valve’s components in order to separate it’s materials.

Before starting the mechanical scrapping procedure wash carefully all the parts of the valve.

The principal parts of the valve are:

VALVE BODY: 

  

AISI 316L (4404)

SHUTTER: 

  

AISI 316L (4404)

ELASTOMETER: 

 EPDM, FKM, SILICONE

                     For the scrapping of the valve the above listied materials are subject to the individual laws governing of the 

                     countries in which the valves are to be scrapped.

Отзывы: