INTRODUCTION
I-E96-314A
6 - 1
SECTION 6 - MAINTENANCE
INTRODUCTION
The frequency control slave requires minimal maintenance.
The following maintenance schedule will ensure troublefree
service.
NOTE: Only qualified personnel should perform maintenance.
MAINTENANCE
The FCS maintenance schedule is shown in Table
. Perform
these tasks at the specified intervals.
REPAIR/REPLACEMENT PROCEDURES
The frequency control slave is designed for long, troublefree
service. There are no parts on the FCS that the user can ser-
vice. If a failure occurs, refer to
for information to
restore operation.
Table 6-1. Maintenance Schedule
Task
Interval
Use static safe vacuum cleaner to
remove dust from:
Modules
Module Mounting Unit
Every 6 months or at plant shut-
down, whichever occurs first.