Stationary VLA Batteries, 

Installation and Operation Instructions 

Page 7 of 17 

w w w. b a e b a t t e r i e s u s a . c o m 

R e v :  0

2

1 9

 

All racks should be properly aligned and all the bolted parts tightened thoroughly before 
placing the cells on them.  Use levelers/shims to compensate for irregularities in the floor 
surface. 

5.1  RACKS (EXISTING RACK

If the cells are to be installed on an existing battery rack, the following inspection should 
be made prior to installation to avoid any possibility of damage to the new battery. 

a) Inspect all bolted connections to make sure that all are properly aligned and tight.

b) Check all painted surfaces making sure everything is clean and free of corrosion.

c) Make sure the rail insulation is clean and in place.

d) If the existing rack is not designed for the new batteries being installed this could

affect your seismic rating and battery warranty.  Please contact BAE USA or your
local representative with questions.

If deficiencies are found with the existing rack - DO NOT INSTALL THE NEW CELLS 
UNTIL CORRECTIVE ACTIONS ARE TAKEN. 

If your inspection indicates that no corrective action is required, proceed with the cell/jar 
installation (go to Section 6.0). 

5.2   RACKS (NEW RACK

Carefully unpack rack materials using care not to scratch the coated surfaces. Check 
received parts against the Bill of Materials for the individual rack. If you find damage to 
the rack components, file a claim against the carrier. 

NOTE:  If rack specific spill containment systems are used, then their installation will 

likely have to be done while installing the rack.  Refer to the manufacturer’s 
recommended installation procedures. 

Refer to the rack assembly drawing and installation instructions and proceed with rack 
assembly. 

When assembled, battery racks must be level and in conformance with the rack
manufacture’s drawings and specifications supplied with the equipment.   This will
ensure that neither individual cells nor rack assembly can topple, twist or overturn.
Use levelers to compensate for irregularities in the floor surface.

Do not place battery cells on the rack until the rack has been completely assembled
with all bolts having been tightened. Otherwise, the weight of the cells may cause the
rack to shift and collapse.

Never remove or loosen braces from a loaded battery rack, removal of braces could
allow the rack to shift or collapse.

If the new rack is not designed for the new batteries being installed this could affect your 
seismic rating and battery warranty.  Please contact BAE USA or your local 
representative with questions. 

6.0  BATTERY CELL/JAR INSTALLATION 

SAFTEY REMINDERS – see Section 1 for details: 

Содержание OPzS Series

Страница 1: ...STATIONARY BAE BATTERIES Vented Lead Acid VLA Flooded Installation and Operating Instructions Important Documents Do Not Discard OPzS OGi Series Batteries...

Страница 2: ...losion and fire hazards exist Acid splashes on the skin must be flushed with plenty of water Acid splashes in eyes must be flushed thoroughly for at least 15 minutes with plenty of water Seek medical...

Страница 3: ...2 ELECTRICAL HAZARDS A filled and charged battery presents a high voltage high current shock and short circuit hazard PRECAUTIONS Observe standard safety measures when working on batteries a Remove w...

Страница 4: ...1 RACKS EXISTING RACK 7 5 2 RACKS NEW RACK 7 6 0 BATTERY CELL JAR INSTALLATION 7 6 1 TERMINAL PREPARATION 8 6 2 INTER CELL CONNECTORS 8 6 3 TERMINAL PLATES 9 6 4 FINAL INSTALLATION STEPS 9 7 0 COMMIS...

Страница 5: ...MISSIONING SA 5 2 0 RECEIVING OF STATIONARY BATTERIES Every precaution has been made in packaging the batteries for shipment to assure their safe arrival IMMEDIATELY upon delivery while carrier delive...

Страница 6: ...ge of 2 23 volts per cell or providing an equalization boost charge to the cells See Section 8 2 Storage at high temperatures results in accelerated rates of self discharge and increases the frequency...

Страница 7: ...lso be used to move the cells If the cells were ordered wet filled immediately check the electrolyte level in each cell or block The electrolyte level should be between the maximum and minimum level l...

Страница 8: ...rack materials using care not to scratch the coated surfaces Check received parts against the Bill of Materials for the individual rack If you find damage to the rack components file a claim against...

Страница 9: ...pacers between the cells during placement of each cell otherwise insufficient spacing may be left to insert them later Install the remaining seismic battery rails for these racks once all cells are in...

Страница 10: ...stallation debris being removed Although already done during unpacking check the electrolyte level in each cell or block to assure spillage has not happened during handling and installation The electr...

Страница 11: ...battery room Additionally please ensure the proper Personal Protection Equipment PPE spill containment or cleanup kit and eyewash are present within the battery room as required per the local or natio...

Страница 12: ...ge of 1 230 to 1 250 kg l Note that the level of electrolyte in the cell will affect the reading see Section 10 5 for details Once the commissioning charge and electrolyte readings are completed if th...

Страница 13: ...age the charging voltage should be decreased by 0 004 volts per 1 C 1 8 F to reduce water decomposition and corrosion Most standard chargers sold today have temperature compensation capabilities to ma...

Страница 14: ...y to charge at a higher voltage See equalization charging Section 8 2 9 0 BATTERY MAINTENANCE Proper maintenance will prolong the life of a battery and will aid in ensuring it is capable of satisfying...

Страница 15: ...corded Quarterly Battery System Voltage Current Section 10 1 Visual inspections o General Appearance Cleanliness o Electrolyte Level o Visible Cell damage Charger output and voltage Ambient temperatur...

Страница 16: ...ue be measured accurately Float current of a fully charged cell under normal conditions is typically 15 to 30 mA per 100 Ah of capacity therefore the measuring device used must be capable of that leve...

Страница 17: ...nections The timing of the corrective action for increased connection resistance should be determined by an analysis of the effects of the increased resistance Consult BAE USA or your local representa...

Страница 18: ...VPC X 60 cells 105 Total Battery Voltage 11 0 6 The capacity test must be terminated when the discharged time assigned to the specific current has been reached or when the final discharge voltage at t...