22

x1

3/8" x 4-1/2" x 48" 

(1 x 11,4 x 121,9 cm)

x1

3/8" x 10-7/16" x 48" 

(1 x 26,5 x 121,9 cm)

PARTS REQUIRED:

FRONT WALL PANELS

x29

2" (5,1 cm)

Install panels in the following order: 

1. 10-7/16" x 48"
2. 1-1/2" x 9" 
3. 4-1/2" x 48" 

Secure panels with 2" nails spaced 6" apart. 

There will be a 5-7/8

"

 reveal at the top of upper panel.

2

10-7/16" x 48"

1-1/2" x 9"

Filler

4-1/2" x 48"

Flush

Flush

Flush

Flush

Center

x1

3/8" x 1-1/2" x 9"

(1 x 3,8  x 22,9 cm)

 5-7/8"

(14,9 cm)

BEGIN HERE

Содержание MODERN 12 x 7

Страница 1: ...AM AND MAKE UP TO 1 500 WEEK o r v i sit backyardinstaller c o m Flexible schedule No selling just building Bonus incentives available S c a n t he f lowcode to apply t o d a y INSTALLERS WANTED based...

Страница 2: ...This page intentionally left blank...

Страница 3: ...our Customer Service Team if engineered drawings are needed to pull local permits SURFACE PREPARATION To ensure proper assembly you must build your shed on a level surface Recommended methods and mate...

Страница 4: ...stallation Level Gloves Framing lumber is graded for structural strength and not appearance Exterior trim is graded for one good side Always install the material leaving the best edge and best surface...

Страница 5: ...Tube For windows and door track Use acrylic latex exterior caulk that is paintable REINFORCED WOOD FLOOR FRAME OPTIONAL IMPORTANT The included floor has been designed for general use Depending on your...

Страница 6: ...96 5 1 x 10 2 x 243 8 cm x1 PT 2 x 3 x 96 5 1 x 7 6 x 243 8 cm x2 2 x 4 x 72 5 1 x 10 2 x 182 9 cm TM x1 3 8 x 1 1 2 x 9 0 9 x 3 8 x 22 9 cm x2 19 32 x 2 1 2 x 58 3 4 1 5 x 6 3 x 149 2 cm TTB x1 3 8 x...

Страница 7: ...6 0 9 x 5 1 x 186 2 cm x1 19 32 x 3 1 2 x 60 1 2 1 5 x 8 8 x 153 7 cm WAB x2 19 32 x 5 1 2 x 70 1 4 1 5 x 14 x 178 4 cm CMB x1 19 32 x 3 1 2 x 59 1 4 1 5 x 8 8 x 150 4 cm HBA x1 19 32 x 3 1 2 x 61 1 1...

Страница 8: ...x 96 1 x 106 7 x 243 8 cm x1 3 8 x 42 x 96 1 x 106 7 x 243 8 cm x1 3 8 x 48 x 84 1 x 122 x 213 4 cm x1 3 8 x 4 1 2 x 48 1 x 11 4 x 121 9 cm x1 3 8 x 10 7 16 x 48 1 x 26 5 x 121 9 cm x2 DOORS 6 x265 2...

Страница 9: ...ate x2 x1 x6 x2 x2 x2 36 91 4 cm Door Brush x2 36 91 4 cm Door Brush Channel x2 69 3 4 177 2 cm Door Brush x2 69 3 4 177 2 cm Door Brush Channel x4 2 5 1 cm x4 x16 1 2 5 cm x8 5 16 x 2 Hex Lag Screw x...

Страница 10: ...ing in water drainage use gravel under each concrete block LEVELING METHODS If you are building your shed on a concrete foundation see the following page CONCRETE MATERIAL REQUIRED x2 4 x 4 x 12 10 x...

Страница 11: ...ll plates Fasten 2 x 4 5 1 x 10 2 cm sill plates to slab using approved concrete anchors fasteners not included Check local code for concrete foundation requirements NOTES Allow new concrete slabs to...

Страница 12: ...r easier nailing stand on frame 1 Secure with 2 3 nails at each mark Orient parts as shown on flat surface Measure and mark BEGIN Your floor frame is now assembled Proceed to level and square frame FI...

Страница 13: ...ame squareness by measuring diagonally across corners If the measurements are the same the frame is square The diagonal measurement will be approximately 169 13 16 431 3 cm When the frame is level and...

Страница 14: ...1 3 Continue attaching the panel with 2 nails spaced 6 apart on edges and 12 apart inside panel Fig A PARTS REQUIRED x1 x53 5 8 x 48 x 96 1 6 x 121 9 x 243 8 cm Grid lines up Seam 2 5 1 cm Flush Flush...

Страница 15: ...FINISH Your floor panels are now installed Continue installing panels with 2 nails spaced 6 apart on edges and 12 apart inside panels 4 x1 x1 x123 5 8 x 48 x 90 1 6 x 60 6 x 122 cm 5 8 x 42 x 96 1 6...

Страница 16: ...rame is level after installing floor panels Re level if needed HINT IMPORTANT The floor should be used as a stable work surface for wall construction Organize your assembly procedure during the build...

Страница 17: ...72 7 cm UM x2 2 x 4 x 48 5 1 x 10 2 x 121 9 cm SP x32 15 3 7 6 cm BEGIN 1 Use 2 3 nails at each mark and 4 3 nails at seams Orient parts on edge on floor Measure and mark 2 UM x7 TP SP SP TP 144 365 8...

Страница 18: ...mark the 3 4 measurement on the wall stud Secure panel with 2 nails spaced 6 apart on edges and 12 apart inside panel 3 3 4 GAUGE BLOCK GAA Primed side up For squareness maintain 3 4 measurement along...

Страница 19: ...ils spaced 6 apart on edges and 12 apart inside panel 4 You have finished building your back wall FINISH 48 x 76 121 9 x 193 cm x2 BACK WALL PANELS PARTS REQUIRED x94 2 5 1 cm Carefully flip the back...

Страница 20: ...enter OSB Build header assembly as shown using 3 and 2 nails Flush Flush 3 1 4 x 66 3 4 OSB 3 1 4 x 66 3 4 OSB x2 7 16 x 3 1 4 x 66 3 4 1 1 x 8 3 x 169 5 cm OSB x2 2 x 4 x 67 5 1 x 10 2 x 170 2 cm AM...

Страница 21: ...EQUIRED HINT For easier nailing stand on frame x2 2 x 4 x 72 5 1 x 10 2 x 182 9 cm TM x2 2 x 4 x 70 1 2 5 1 x 10 2 x 179 1 cm AYA x4 2 x 4 x 72 1 2 5 1 x 10 2 x 184 2 cm PTA x2 2 x 4 x 86 1 8 5 1 x 10...

Страница 22: ...re with 2 3 nails at locations shown Secure with 4 3 nails into each side of header Install door header with OSB to the top of header Secure header with 3 nails at locations shown 3 4 FRONT WALL FRAME...

Страница 23: ...ove top plate Secure panel with 2 nails spaced 6 apart along edges and 12 apart on inside of panels There will be a 5 7 8 reveal at the top BEGIN 1 FRONT PANELS ARE FRAGILE UNTIL INSTALLED HANDLE CARE...

Страница 24: ...2 5 1 cm Install panels in the following order 1 10 7 16 x 48 2 1 1 2 x 9 3 4 1 2 x 48 Secure panels with 2 nails spaced 6 apart There will be a 5 7 8 reveal at the top of upper panel 2 10 7 16 x 48...

Страница 25: ...screws MAINTAIN 64 DIMENSION BETWEEN STUDS Carefully flip the front wall over 4 Install 2nd 48 x 96 panel flush to frame as shown and 5 7 8 from the top Secure panel with 2 nails spaced 6 apart along...

Страница 26: ...B 4 2 3 7 6 cm x12 2 5 1 cm x27 BACK WALL INSTALLATION D O O R 3 Nails into bottom plate 3 7 6 cm Screws x2 BEGIN Center back wall assembly on the 144 floor dimension Note The 4 wall overhang is insta...

Страница 27: ...all assembly on the 144 front floor dimension Use 2 OFB as temporary braces Level wall and secure OFB with 3 screws 2 1 144 365 8 cm Nail 2 nails first 2 5 1 cm Nails 3 7 6 cm Nails Fig A Secure lower...

Страница 28: ...m SP x2 2 x 4 x 96 5 1 x 10 2 x 243 8 cm TP BEGIN 1 2 TP SP 3 7 6 cm Nails Stagger seams Flush Flush 3 7 6 cm Nails Flush Flush Flush at seam Flush at seam Center doublers SP and TP on back wall top p...

Страница 29: ...DC 2 5 1 cm Screw 2 5 1 cm Screw BEGIN Install rafters on front and back wall doublers Ensure rafters are flush to end of top plates Fig B Fig D Secure rafters as shown in all Figures 1 2 5 1 cm Screw...

Страница 30: ...28 OUTER RAFTER INSTALLATION PARTS REQUIRED x20 1 1 2 3 8 cm x2 H 2 5 Tie Plate Attach tie plates using 1 1 2 nails as shown 2 Your outer rafters are now installed FINISH 1 1 2 3 8 cm Nails...

Страница 31: ...ered into outer rafter ends Fig A Continue securing rafters using 3 screws angled into doublers Fig B 2 BEGIN Measure and mark location of each rafter Note the door location 1 BEGIN HERE 10 25 4 cm 26...

Страница 32: ...30 RAFTERS PARTS REQUIRED Your rafters are now installed FINISH x9 H 2 5 Tie Plate Attach 9 tie plates using 1 1 2 nails as shown Fig A 3 FRONT 1 1 2 3 8 cm x90 1 1 2 3 8 cm Nails Fig A...

Страница 33: ...ils in the bottom corners Fig A Angle nails to hit floor frame Fig C Center and attach OO as a temporary support Measure down from floor 1 and mark Secure to floor joist using 2 3 screws Push the fron...

Страница 34: ...measurement between the panel edges are the same along the corner Fig F Secure panel with 1 1 1 2 nail in upper corner 4 Primed side out 2 Nail Flush Panels Flush at bottom 5 Secure lower edge of pan...

Страница 35: ...side side wall studs 3 Fig B Fig A Center NES on seam of wall panels KTB NES OFB 3 7 6 cm Screw D O O R MARK BEGIN Install NES centered at seam of side wall panels Fig A Use a square to ensure 90 degr...

Страница 36: ...anel with 2 1 1 2 nails Flush filler panel to installed panels Red for right side as shown Measure and mark location of studs 20 from center of panel seam as shown Secure side wall panels to inside wa...

Страница 37: ...all the 10 11 16 x 96 lower roof panel to the chalk line Ensure the panel measures 3 4 on the rafter center Fig B Secure panel with 2 nails as shown D O O R D O O R Place the 10 11 16 x 31 7 8 and 10...

Страница 38: ...the roof by attaching one 48 x 96 panel at this time Use the panel s long edge as a lever to bring your roof into square Place the 48 x 96 roof panel as shown Use the gauge block to maintain 3 4 at r...

Страница 39: ...enter Secure panel with 1 2 nail in each corner Install 3rd 48 x 96 panel flush to installed panels Maintain 3 4 at rafter center Secure panel with 1 2 nail in each corner Install 11 7 8 x 96 panel fl...

Страница 40: ...8 ROOF PANELS PARTS REQUIRED 2 5 1 cm Complete the securing of all upper roof panels with 2 nails 6 along edge and 12 inside panel 7 Your roof panels are now installed FINISH 6 15 2 cm 12 30 5 cm x160...

Страница 41: ...s with 2 screws through roof panels Fig A Use 4 screws at roof panel seams Install QVA extensions flush with side wall panels Fig B HINT Use screws at rafter ends as a guide to line up QVA with rafter...

Страница 42: ...ING 1 Align THB edge flush with rafter extension Fig A Attach with 3 2 nails Fig B BEGIN HJ THB 2 3 Attach HJ flush with THB with 5 2 nails Fig A FIg B Repeat STEPS 1 2 on opposite side You have finis...

Страница 43: ...e down flush to front wall panel Fig A Secure to side rake frame THB using 7 2 finish nails Fig A B Repeat STEP 1 on opposite side BEGIN Your side soffit panels are now installed FINISH 3 2 Finish Nai...

Страница 44: ...ns and flush to side wall soffit Fig A Ensure each soffit is flush to front wall panel Secure soffit panels using 2 2 finish nails into each rafter extension Use 4 finish nails at seam Fig B BEGIN PAR...

Страница 45: ...g A Right side of WAB is approximately 3 4 from center of rafter extension Secure WAB with 2 finish nails into rafter extensions Fig B BEGIN 1 x1 19 32 x 3 1 2 x 60 1 2 1 5 x 8 8 x 153 7 cm WAB 2 Fini...

Страница 46: ...ing your front fascia Position ZX primed side out flush with WAB and flush up under roof panels Secure ZX with 2 finish nails into rafter extensions Fig B 2 19 32 x 3 1 2 x 96 1 5 x 8 8 x 243 8 cm x1...

Страница 47: ...15 16 5 1 x 7 6 x 81 1 cm RMA x2 19 32 x 3 1 2 x 45 1 5 x 8 9 x 114 3 cm WQA x1 19 32 x 3 1 2 x 61 1 16 1 5 x 8 9 x 155 1 cm UDR x1 19 32 x 3 1 2 x 61 1 16 1 5 x 8 9 x 155 1 cm UDL x2 OY 2 x 3 x 72 5...

Страница 48: ...ig A Fig B x18 2 5 1 cm Secure fascia assembly under roof panels flush with front fascia board using 6 2 screws through roof sheathing Fig A 2 x1 LEFT FASCIA ASSEMBLY LEFT FASCIA ASSEMBLY FRONT WALL R...

Страница 49: ...on opposite side to install right fascia 4 Secure front fascia to side fascia with 2 2 finished nails Fig D x18 2 5 1 cm Nail up through side soffit into fascia assembly using 7 2 finish nails Fig C 3...

Страница 50: ...R FASCIA TRIM PARTS REQUIRED 48 x2 x10 2 5 1 cm 3 7 6 cm BEGIN 1 Install PT and GKA using 2 wood screws through roof sheathing Fig A Secure PT and GKA using 1 3 screw through side fascia trim nailer O...

Страница 51: ...1 2 x 96 1 5 x 8 8 x 243 8 cm x1 ZX REAR FASCIA TRIM PARTS REQUIRED 49 x14 2 5 1 cm Secure HBA and ZX to PT and GKA with 2 finish nails Fig C Ensure trim is primed side out 3 FINISH Your rear fascia t...

Страница 52: ...r trim is now installed FINISH 2 5 1 cm Finish Nail Flush to soffit board Fig A 73 5 16 Corner Trim SIDE WALL PANEL Place 73 5 16 back corner trim flush to bottom of back soffit board Fig A and flush...

Страница 53: ...PS 1 2 for opposite side Install 93 1 8 side front corner trim flush to front wall panel Fig A Secure trim with 9 2 finish nails spaced evenly Install 73 7 16 side back corner trim flush to back wall...

Страница 54: ...ails evenly Install 2 ZD trim pieces centered and flush up to soffit Secure trim with 14 2 finish nails into top plate Space nails evenly BEGIN 1 2 CENTER VAA VAA ZD ZD Fig A Flush to side corner trim...

Страница 55: ...ter of opening and level Secure with 4 screws on sides of each window Apply high quality exterior grade caulk behind frame near edge before installing to seal window 2 You must caulk around windows to...

Страница 56: ...oor opening Secure with 18 2 finish nails as shown Space nails evenly Center 5 EY on gap between window frames as shown Secure with 10 2 finish nails into framing x5 19 32 x 2 1 2 x 9 1 5 x 6 4 x 22 9...

Страница 57: ...d installing your windows and window trim FINISH Install 4 3 4 screws from inside into window trim as shown Do not screw into window flange NOTE Snip off protruding finish nails from inside of front w...

Страница 58: ...between doors Secure with 11 3 4 special coating screws into floor Install TJB flush to lower window trim and flush to front panels Secure trim with 2 finish nails BEGIN 1 2 5 1 cm x14 Flush Flush Flu...

Страница 59: ...ndow trim into header Fig A Slide left rail inside right track bracket flush to right track rail Fig B Mark bracket hole locations on window trim Pre drill holes using a 1 8 drill bit Secure track wit...

Страница 60: ...R REINFORCEMENT x2 PARTS REQUIRED 3 4 1 9 cm x60 Reinforce doors by back screwing through inside of door panel into trim Use 30 3 4 screws in each door according to pattern shown Space screws evenly B...

Страница 61: ...l 36 rain channel flush to end centered across upper corner of door Secure with 3 4 screws spaced evenly approx 8 BEGIN 1 Metal Rain Channel x2 1 x 1 x 36 2 5 x 2 5 x 91 4 cm Flush Flush Flush 8 20 3...

Страница 62: ...mp each end of channel Fig B 2 BEGIN 1 PARTS REQUIRED x2 36 91 4 cm Door Brush x2 36 91 4 cm Door Brush Channel 3 4 1 9 cm Screws INSIDE OF DOOR 1 1 4 3 2 cm 8 X 3 4 1 9 cm Self Piercing Round Head Sc...

Страница 63: ...EQUIRED Install 2 rolling door trolleys to inside top of each door using screws supplied in rolling door hardware bag Position as shown BEGIN 1 4 1 4 10 8 cm 4 1 4 10 8 cm x16 1 2 5 cm TAB flush to to...

Страница 64: ...62 DOOR INSTALLATION Slide right and left door into track as shown Fig A BEGIN 1 x2 PARTS REQUIRED Fig A NOTE Install doors into track slowly to prevent damage to rain channel...

Страница 65: ...of left door Weatherstrip should be flush to bottom of over door trim and overhanging 1 2 past edge of door Fig A Fig B 1 PARTS REQUIRED WEATHERSTRIP 1 2 13 mm 1 2 13 mm 1 2 13 mm 1 2 13 mm Flush Flus...

Страница 66: ...outside secure OO with 7 2 screws through trim into OO Fig D Space screws evenly FINISH 2 Fig C Center OO vertically PARTS REQUIRED DOOR STIFFENERS 2 5 1 cm Screws x14 11 27 9 cm Approximately x14 2...

Страница 67: ...screws Fig A Pre drill using a 1 8 drill bit BEGIN 1 1 8 BIT 3 0 mm PARTS REQUIRED 2 5 1 cm x4 42 106 7 cm 2 5 1 cm Pan Head Screws Refer to latch hardware packaging instructions for installation Ins...

Страница 68: ...If the door hits the stay roller bracket move the bracket slightly down until the door clears the bracket Fig B then install the bracket Fig A Loosen nut and move roller until door is hanging free Ad...

Страница 69: ...RIM OVER DOOR 3 4 1 95 cm Screws SAFETY Door Stop must not protrude in doorway Install door stop centered on over door trim seam and flush to bottom of trim as shown Secure with 4 3 4 screws Flush PAR...

Страница 70: ...shown Assemble 2 69 3 4 door brushes as shown in STEP 1 PAGE 59 Fig A and Fig B BEGIN 1 PARTS REQUIRED x2 69 3 4 177 2 cm Door Brush x2 69 3 4 177 2 cm Door Brush Channel Fig C D O O R 3 4 1 9 cm Scre...

Страница 71: ...ter location of spring bolt pin on metal threshold Fig C Raise spring bolt pin and slide door open Pre drill metal threshold at mark using a 3 16 bit Re drill hole using a 3 8 bit Drill at least 1 1 2...

Страница 72: ...as shown 1 at top and 1 at bottom Cut out marked openings Caulk behind vent flanges Secure with 1 2 screws Your vents are now installed x12 1 2 1 3 cm x2 8 x 16 20 3 x 35 6 cm 6 15 2 cm 3 5 7 6 12 7...

Страница 73: ...med exterior wood before painting Follow directions provided by manufacturer PAINT CAULK NOT INCLUDED Cut drip edge flush to trim BACK OF SHED Cut drip edge flush to trim NOTE Install drip edge to bac...

Страница 74: ...first 3 Install side drip edge flush along roof panels Flush ends to trim Fig A Secure with 1 roofing nails spaced 6 apart Only nail top of drip edge OVERLAP 16 TYP 40 6 cm 1 Roofing Nails Drip Edge...

Страница 75: ...nstall first starter row upside down color up and flush to drip edge at bottom of roof panel Use 4 nails per shingle Starter row must be straight and level all the way across with lower edge of roof d...

Страница 76: ...shed make sure there is a maximum of 5 or less to the rain slot as shown below If shingles overlap at front roof edge cut to roof edge with a utility knife 1 2 5 cm 5 12 7 cm 5 12 7 cm or less BACK OF...

Страница 77: ...w with 1 overhang over roof edge Align remaining shingles with edge of the front drip edge Using your shingle hooked blade carefully cut shingles on a flat surface along the rain slots using a chalk l...

Страница 78: ...G 1 1 2 X 9 K 09000108000 1 Side Soffit Panels 3 8 NG 5 1 4 X 94 7 16 SOFFIT K 94070504000 2 Right Wall Filler 3 8 NG 2 11 16 X 12 1 4 WALL FILLER K 12040211100 1 Left Wall Filler 3 8 NG 2 11 16 X 12...

Страница 79: ...siding trim and OSB siding to include all exterior walls and all sides and all edges of doors Gazebos Pergolas To validate your warranty it is necessary to properly maintain your Backyard Storage Solu...

Отзывы: