GENERAL MAINTENANCE INSTRUCTIONS: 

 

 

Check MONTHLY for loose bolts, damaged or broken parts.  Tighten and/or 
replace immediately. Replace any parts that show a reduction of 25% 
from the original size. 
 

GENERAL ASSEMBLY INSTRUCTIONS: 

 
Check all the parts and hardware with the packing list to be sure you 
have received everything needed to assemble this product.  CONTACT YOUR 
LOCAL DISTRIBUTOR WITH NOTIFICATION OF ANY MISSING OR DAMAGED PARTS.  
Contact must be made within ten days of receipt of your order. 
Only hand-tighten nuts & bolts on initial assembly.  Final tightening 
should be done EVENLY after final assembly when unit has been plumbed & 
leveled.   
After assembly is complete, ANY ENDS OF BOLTS PROTRUDING BEYOND NUTS 
SHOULD BE CUT OFF AND/OR PEENED OVER TO REMOVE ANY SHARP EDGES.  Go 
over entire unit to file smooth any sharp edges or projections that may 
have been caused by rough handling in shipping or installation.  
 

ASSEMBLY AND INSTALLATION: 

 

 

NOTE: 

All threaded ends of bolts protruding beyond nuts must be cut off 
and/or peened to eliminate sharp edges.  No more than two threads 
should extend beyond face of nut. All washers, “T” nuts, and 
other fastener hardware used on round pipe or tubing must be 
hammered down to conform to the curved underlying surface to 
eliminate catch points. All Bolts must be covered with Bolt Caps 
and Covers 
 

 

STEP #1:  Using all of the Footing Diagrams as a guide, mark and dig 

footing holes starting with the holes for the main posts.  Add 
concrete only after the entire unit is assembled.  Total footing 
depth including the surfacing is 2’ 6”.  If you use 12” of 
surfacing than the actual hole will be 1’ 6”.  Footing depths 
vary by location.  You must check local building codes for 
requirements.  Should the building code require a deeper footing 
the actual post depth cannot change because it would throw off 
the overall height of the equipment.  Add a brick or solid object 
to the deeper hole and keep the post at the proper height. 

STEP #2:  Attach the Aztec Plastic Panel to the Aztec Panel Ground Anchor 

by placing the Plastic Panels over the tabs of Ground Anchors.  

Note

The King Figure must be on the lower left. 

 
 
 
 
 
 
 
 
 
 
 
 
 

 

Содержание 902-757 Corkscrew

Страница 1: ...improperly maintained can cause serious injury Periodical inspections maintenance repair and or replacement of damaged parts is necessary for safe operation of equipment Appropriate publications avai...

Страница 2: ...ngs illustrated are satisfactory in most applications for pipe sizes up to 4 diameter Varying soil climatic conditions may require deeper and heavier footings in some areas Check local building codes...

Страница 3: ...902 757 Corkscrew Aztec Climber Page 3 Rev 04 9 2010 SportsPlay Equipment Inc 5642 Natural Bridge St Louis MO 63120 314 389 4140 www sportsplayinc com Complete Footing Layout...

Страница 4: ...902 757 Corkscrew Aztec Climber Page 4 Rev 04 9 2010 SportsPlay Equipment Inc 5642 Natural Bridge St Louis MO 63120 314 389 4140 www sportsplayinc com Footing Layout Close up of the ends...

Страница 5: ...902 757 Corkscrew Aztec Climber Page 5 Rev 04 9 2010 SportsPlay Equipment Inc 5642 Natural Bridge St Louis MO 63120 314 389 4140 www sportsplayinc com...

Страница 6: ...902 757 Corkscrew Aztec Climber Page 6 Rev 04 9 2010 SportsPlay Equipment Inc 5642 Natural Bridge St Louis MO 63120 314 389 4140 www sportsplayinc com Use Zone...

Страница 7: ...in shipping or installation ASSEMBLY AND INSTALLATION NOTE All threaded ends of bolts protruding beyond nuts must be cut off and or peened to eliminate sharp edges No more than two threads should exte...

Страница 8: ...bolt cap and securing to the bolt from the opposite side Repeat this process for the other two holes STEP 4 Repeat Steps 1 2 and 3 with other Ground Anchor and Plastic Panel STEP 5 Attach the other si...

Страница 9: ...in turn to Horizontal Connecting Post Secure using same technique as before Note The Dragon Figure must face upwards as shown below STEP 8 Using the same technique as was used in the previous step at...

Страница 10: ...slight dome to ensure proper drainage Wait 48 hours before removing braces Install resilient safety surfacing STEP 10 Attach Warning Label and Manufacturer s Identification Label to a clean surface T...