Instruction manual Civil V1.0 _ XX-09-2020 _ FttX-Distribution Closure AT29030 _ Page 2 of 6
1. Strip 70cm of the DB-duct 2x Ø14/10mm.
2. Remove the base plate from the packaging.
Place the base plate on a flat surface in the
trench.
3. Seal the ports (preferably port 2 + 3) that
will
NOT
be used. Do this by sliding the port
seal
A
under the hooks and placing the
foam strips
B
over the hooks of the base
plate.
4. Push the DB ducts through the base plate's
hooks until they are 50 cm from the port.
Provide both ducts with an end cap.
In case that a window cut needs to be
made, then follow step 4 for both sides.
This should then look like this (see photo).
5. Push the customer cables / ducts on both
sides through the hooks of the base plate.
Max capacity per port:
2x Ø14/10mm + 48x Ø6 mm or
2x Ø14/10mm + 30x Ø8 mm
6. Take the foam port seals (
A
) out of the
packaging.
Keep the foam seals (
B
) separate for now.
They are to be used in step 11.
Fold the foam port seal
A
, including the
core, around the bundle of cables/ducts.
1
2
3
4
50 cm
70 cm