Operation
ASCO Model K875A Outdoor Load Bank
4-8
Method 2
- Rough Adjustment
NOTE
Adjustable potentiometers on the controller board have a % scale
reference that directly relates to the current, (Isense), delivered from
the current transformer used to monitor the building load. Refer to
Secondary Current Calculation
, in
Trip Point Section
of this
manual. The scale is based upon a 5 amp input.
.5 amp
= 10% Dial Setting
1.25 amp
= 25% Dial Setting
2.5 amp
= 50% Dial Setting
3.75 amp
= 75% Dial Setting
5.0 amp
= 100% Dial Setting
With all power removed from the Load Bank, calculate each desired Trip Point and adjust the
potentiometers (R21, R34, R47, R60, R73) in order to achieve a rough adjustment controller setting.
NOTE
The current sense relay settings must be set sequentially. It is
extremely important that the sequence be correct because the current
sense relays are interlocked by the previous relay. Consult the
factory at 216-573-7600 if unsure of proper adjustment.