2.8

 

Assembly Instructions  

 

Check that all materials meet the annual inspection labels and check all materials for damage. If in 
doubt, contact ASC or your dealer for any questions. Aluminum Scaffoldings should only be erected 
by people with enough and proven experience.  
  

Floor height 0.70 m (A)

 

 

 
1. 

Insert the wheels (

8

) into the folding unit 6-rung (

1

) at the bottom 

and secure with a locking clip (

9

).  

2. 

Open the folding unit, place the platform without trapdoor (

3

) on 

the 2

nd

 rung and secure the folding unit with a locking clip in the 

hinge piece.  

3. 

Put the wheels (

8

) on the brake and place a horizontal brace (

4

) on 

the upper rung (opposite the folding unit). This will create a handrail 
at hip height.  

5. 

Put the side board holders (

7

) to the upright on the top work floor 

and place the side boards in the slots of the side board holders. 

6. 

Check again that the scaffolding is properly positioned, the wheels 
are on the brake and the stabilizers are firmly on the ground. 

 

If you place the platform on the 3rd rung or higher, you will need all the parts from the 
composition KMA2 (B). 

 

Floor height 1.85 m (B) 

 
1. 

Place the wheels (

8

) in the folding unit 6-rung (

1

) at the bottom and secure with a locking clip 

(

9

).  

2. 

Open the folding unit, place the platform with trapdoor (

3

) on the 5

th

 rung and secure the 

folding unit with a locking clip in the hinge piece.   

3. 

Place the (tele-)stabilizers (

6

) and make sure they are firmly on the ground. Always place a 

stabilizer link under a rung (to prevent slipping). For the correct assembly see section 2.5.4. 

4. 

Open the folding unit 3-rung (

2

) on the ground, click in 2 horizontal braces (hip and knee 

height) and assemble it in the same form as the underlying folding unit. Secure all uprights 
with locking clips.   

5. 

Climb up on the inside and snap the side board holders (

7

) to the upright on the top work 

floor and place the side boards in the slots of the side board holders. 

6. 

 Check again that the scaffold is properly positioned, the wheels are on the brake and the 
stabilizers are firmly on the ground. 

 

Floor height 2.70 m (C) 

 
1. 

Insert the wheels (

8

) into the folding unit 6-rung (

1

) at the bottom and secure with a locking 

clip (

9

).  

2. 

Open the folding unit, place the platform with trapdoor (

3

) on the 2

nd

 rung and secure the 

folding unit with a locking clip in the hinge piece.   

3. 

Place the (tele-)stabilizers (

6

) and make sure they are firmly on the ground. Always place a 

stabilizer link under a rung (to prevent slipping). For the correct assembly see section 2.5.4. 

4. 

Open the 2

nd

 folding unit 6-rung (

1

) on the ground, click in 2 horizontal braces (hip and knee 

height) and assemble them on top of each other in the same shape as the underlying folding 
unit. Secure all uprights with locking clips.   

 

Содержание ASC Folding Tower

Страница 1: ...This manual is property of ASC Group Leerlooierstraat 32 4871 EN Etten Leur Nederland Manual ASC Folding Tower Conform EN1004 2 Manual ASC Folding Tower Conform EN1004 2 ...

Страница 2: ... provided with the utmost care by ASC Group All rights reserved No part of this publication may be reproduced stored in a retrieval system or transmitted in any form or by any means electronic mechanical photocopying recording or otherwise without the prior written permission from ASC Group This publication may only be used for ASC Group products Typesetting and printing errors reserved If you hav...

Страница 3: ...se 5 2 5 Positioning of the Mobile Folding tower 5 Sureface 5 Obstacles 5 Maximum height 5 Weather conditions 5 2 6 Personal protection equipment 5 2 7 Assembly 5 2 8 Assembly Instructions 6 2 9 Use 8 Extension increase 8 Maximum permissible weight 8 Further loads weights 9 Stabilization 9 Sideboard set 9 Security 9 Relocation 9 2 10 Chemical products 9 3 Inspection care and maintenance 9 3 1 The ...

Страница 4: ...r the contact information is at the front of this brochure 1 2 List of components 1 Folding unit 6 rung 2 Folding unit 3 rung 3 Platform with without trapdoor 4 Horizontal brace 5 Diagonal brace 6 Tele Stabilizer 7 Wheel 200mm 8 Side board set incl 4 holders 9 Locking clips Composition Floorheight 0 70 1 85 2 70 3 70 4 50 5 50 Articles Folding unit 6 rung 1 1 1 2 2 3 3 Folding unit 3 rung 2 1 1 Gu...

Страница 5: ... extra effort Maximum height This depends on the placement and type of Folding tower see Table 1 Weather conditions Consult the weather report to determine safety in various weather conditions Consider the following conditions and use common sense Wind force Precipitation Remove snow and ice from the Folding tower before starting work If necessary sprinkle sand on the work floor to prevent slippag...

Страница 6: ... 8 in the folding unit 6 rung 1 at the bottom and secure with a locking clip 9 2 Open the folding unit place the platform with trapdoor 3 on the 5th rung and secure the folding unit with a locking clip in the hinge piece 3 Place the tele stabilizers 6 and make sure they are firmly on the ground Always place a stabilizer link under a rung to prevent slipping For the correct assembly see section 2 5...

Страница 7: ...es knee and hip height before standing on the platform 6 Attach a diagonal brace 5 to the 5th to the 10th rung 7 Mount the 2nd platform with trapdoor 3 on the 5th rung of the 2nd folding unit 8 Open the folding unit 3 rung 2 on the ground click in 2 horizontal braces hip and knee height and assemble it in the same form as the underlying folding unit Secure all uprights with locking clips 9 Climb u...

Страница 8: ...e 1st to the 5th rung 5 Mount the 3rd platform with trapdoor 3 on the upper rung of the 3rd folding unit 6 While sitting on the platform assemble the guardrail frame on the left and right sides and on both sides 2 horizontal braces at knee and hip height A handrail is created all around 7 Click the toe board holders 7 to the upright on the top work floor and place the toe boards in the slots of th...

Страница 9: ...a fixed object with a ring lock To do this put the ring lock through one of the frame s compartments and attach an anti climb device Relocation A mobile Folding tower can be moved by dismantling and rebuilding it After moving the Folding tower it must be put back into plumb therefore go through the checklist again from Section 2 9 2 10 Chemical products 3 Inspection care and maintenance According ...

Страница 10: ...r other non removable contamination on the components the Folding tower must be rejected after all you can no longer judge whether the components are still intact What to do in the event of damage If there is any damage which cannot be repaired the component must be taken out and replaced If repairing is possible please contact ASC Group for further information Repair 3 2 Transport Always transpor...

Отзывы: