Horizontal or ceiling installation
Using the paper template, trace on the ceiling the position
of the two fixing brackets and the two rear screws. Using
a suitable drill, make the holes and insert the wall plugs (2
for each bracket); fix the two brackets. Do not over-tighten
the screws. Position the machine on the two brackets,
keeping it in position and then fix the two screws into the
rear toggle bolts, one on each side.
Make sure that there is sufficient inclination of the unit
towards the drainage pipe to facilitate the water drainage.
Fully tighten all 6 fixing screws.
For horizontal or ceiling-mounted installation, the following
horizontal condensate collection basin kits are available
as accessories: 3301561 - 3301562 - 3301563 - 3301564.
Carefully check the inclination of the exhaust pipe.
Any counterslope of the discharge line can cause
water leakage.
Wall plugs
Brackets
Screws
Drainage pipe
Hydraulic connections
The choice and sizing of the hydraulic lines must be made
by an expert who must operate according to the rules of
good technique and the laws in force, taking into account
that undersized pipes cause a malfunction.
To make the connections:
-
position the hydraulic lines
- tighten the connections using the “spanner and
counter spanner” method
-
check for any leaks of liquid
-
coat the connections with insulating material.
The hydraulic lines and joints must be thermally insulated.
Avoid partially insulating the pipes.
Do not over-tighten to avoid damaging the insulation.
Use hemp and green paste to seal the threaded
connections; the use of Teflon is advised when there is
anti-freeze in the hydraulic circuit.
Pipeline diameter