Quick Start Guide: 7300 Series Modular Data Center Switches
7
Chapter 2
Preparation
2.1
Site Selection
The following criteria should be considered when selecting a site to install the switch:
Floor Space:
Install the switch in an area that provides adequate clearance for removing front and rear
components.
displays switch clearance requirements.
Figure 2-1: Switch Component Removal Footprint
•
Temperature and Ventilation:
For proper ventilation, install the switch where there is ample
airflow to the front and back of the switch. The temperature should not go below 0° or exceed 40° C.
Important!
To prevent the switch from overheating, do not operate it in an area where the ambient temperature
exceeds limits specified in
.
•
Airflow Orientation:
Determine airflow direction of the fan modules and power supply modules.
Fan and power supply module handles indicate airflow direction:
•
Blue Handle
: Air Inlet module.
•
Red Handle
: Air Exit module.
displays power supply module locations on the front panel.
displays fan
module locations on the rear panel (DCS-7316 switches may also contain rear panel power supply
modules). Verify the airflow direction of all modules satisfy these criteria:
•
All rear panel modules have the same color handles.
Содержание DCS-7304
Страница 10: ...6 Quick Start Guide 7300 Series Modular Data Center Switches Specifications Chapter 1 Overview ...
Страница 48: ...44 Quick Start Guide 7300 Series Modular Data Center Switches Two Post Rack Mount Parts Appendix C Parts List ...
Страница 52: ...48 Quick Start Guide 7300 Series Modular Data Center Switches Appendix D Front Panels ...
Страница 55: ...Appendix E Rear Panels Quick Start Guide 7300 Series Modular Data Center Switches 51 DCS 7316 Rear Panel ...
Страница 56: ...52 Quick Start Guide 7300 Series Modular Data Center Switches Appendix E Rear Panels ...
Страница 58: ...54 Quick Start Guide 7300 Series Modular Data Center Switches Appendix F Line Cards DCS 7320X 32C LC ...