background image

EZINST-1/7/16

Page 4 of 12

© Aqua Creek Products LLC 2003-2016

EZ POOL LIFT ANCHOR INSTALLATION

EZ POOL LIFT RETRO-FIT ANCHOR INSTALLATION

STEP 1:

Determine the best location for the lift. Be sure to mount the lift at a location that provides
at least 42” [107 cm] and no more than 48” [122 cm] from deck level to the bottom of the
pool. Make sure the location includes enough clear deck space to easily transfer into the
lift seat. Keep in mind this lift will require assistance from another person to operate and
you should locate it in an area that can accommodate another person. The lift should also
be located so as to provide at least 6’ [1.8 m] of unobstructed deck to each side of the lift
to accommodate easy maneuvering of the lift over the
water and back.

STEP 2:

Locate the concrete anchor socket that came with your
lift. Be careful to not lose the protective cap on the
anchor. This will be used to keep dirt and debris out of
the socket when the lift is not installed in the anchor.

STEP 3:

The setback to the center of the anchor must be no less
than 12” [30.5 cm] and no more than 20” [51 cm] from the pool wall. The anchor location
must also be at least 6” [15 cm] from any control joint or edge of concrete slab. Measure
the location out using your tape measure and marking pen. (Reference the drawing on the
next page for details).

NOTE:

The EZ Pool Lift comes standard with a 6” deep anchor socket that is

installed into a concrete deck. Anchor options include a surface mount anchor
and a wood deck anchor system both purchased separately. The EZ Pool Lift
standard 6” anchor system can be installed in an existing pool deck (Retro-fit
installation) or when pouring a new concrete pool deck (New construction
installation). If the anchor has already been installed you can move on to the
assembly section of this manual that is appropriate to the lift you purchased.

REQUIRED TOOLS (Core Drilling Method)

Tape Measure

Core Drill

4” [10 cm] Core Drill Bit

Electrical tape

2-part Epoxy or Hydraulic Cement

Small Carpenters Level

Felt Tip Marking Pen

Vacuum or compressed air source

CONCRETE ANCHOR

SOCKET

NOTE:

The concrete deck around the anchor system should be a minimum of 8”

thick and should be reinforced with #4 reinforcing bars spaced on 10” centers in
each direction. The total concrete pad area should be at least 60” wide
(measured away from the pool edge) and 60” long (parallel with the pool edge).

Содержание F-03EZPL

Страница 1: ...ns 400 LBS 181 kg MAXIMUM LIFTING CAPACITY WARNING IMPORTANT SAFETY INSTRUCTIONS 1 READ AND FOLLOW ALL INSTRUCTIONS LIFT SAFETY CAN ONLY BE ENSURED IF THE LIFT IS INSTALLED AND OPERATED PROPERLY ACCOR...

Страница 2: ...Z Pool Lift Parts Lists 3 Retro fit anchor Installation Instructions 4 New construction anchor installation instructions 6 EZ Pool Lift Assembly Instructions 7 EZ Pool Lift Operating Instructions 9 Sa...

Страница 3: ...RDERED 7 2 3 8 X 1 3 4 HEX BOLT S S 8 4 3 8 FLAT WASHER S S 9 2 3 8 NYLOCK NUT S S 10 1 EZ POOL LIFT MANUAL READ CAREFULLY Check entire box and inside all packaging materials for parts Before beginnin...

Страница 4: ...rom the pool wall The anchor location must also be at least 6 15 cm from any control joint or edge of concrete slab Measure the location out using your tape measure and marking pen Reference the drawi...

Страница 5: ...o stop drilling STEP 5 Clean out the hole and make sure your hole is deep enough to allow the anchor to be flush with the finished deck surface STEP 6 Ground the anchor according to your local code re...

Страница 6: ...er of the anchor must be no more than 20 51 cm from the pool wall and at least 6 15 cm from any control joint or edge of concrete slab Measure the location out using your tape measure Reference the dr...

Страница 7: ...ock nut STEP 2 Connect the lower end of the hydraulic ram to the mast with one 1 3 8 x 1 3 4 hex head bolt two 2 3 8 flat washers and one 1 3 8 nylock nut STEP 3 Install lift into previously installed...

Страница 8: ...that the sling is at the appropriate height to allow the user easy access and so that the sling will clear your pool wall if applicable Assembly is complete Prior to lifting any persons in the lift i...

Страница 9: ...till in the wheelchair Attach the chain to the mesh sling and the overhead hanger bar There should not be any slack in the chain at this time Make sure all chain connections are secure and the mesh se...

Страница 10: ...ease to the terminals after cleaning them This will help to prevent further corrosion Do not leave the battery on the lift Always store the battery on the charger whenever the lift is not being used I...

Страница 11: ...NDARD 6 1 F 031EZCH CHAIN SET EZ 7 1 F 032EZB SLING BARS ONLY SETOF 4 8 1 A 0808EZTB SPEZ EZ PEZROTATE HANDLE 9 2 BH3 8 X1 3 4 BOLT 316 SS 3 8 16 X1 3 4 HCS 10 5 WF 3 8 WASHER FLAT 3 8 316 SS 11 3 NN...

Страница 12: ...umber the dates of purchase and installation and the exact nature of the defect Within thirty 30 days after receipt of a written warranty claim by Aqua Creek and barring any unforeseen delays the plac...

Отзывы: