OPT700/OPT700L Installation/User Manual

10

Installation Procedures

Figure 6

NOTE:

1. Step 1~4 can change sequence for convenience of installation.

2. Warranty card is located in Appendix last page of this manual.

Step 5 - Verifying Proper Optimizer Connection

When connected to the PV modules and exposed to light, the APsystems

optimizer will output a PV open circuit voltage. Therefore, the total string
voltage should be equal to the PV open circuit voltage times the number of

power optimizers connected in series in the string. The correctness of the

APsystems optimizer connection can be verified by measuring the polarity

and magnitude of the total string output voltage.

For example, each APsystems optimizer connect to two PV modules and

produce a PV open circuit voltage of 80V. If ten APsystems optimizers are

connected in a string, and then 800V should be produced.

If the measured open circuit voltage is abnormal, please see Troubleshooting

(p.10).

WARNING:

DO NOT connect to other optimizer strings or the

inverter before verifying the optimizer connection. Output value

or wrong polarity will damage the optimizers or inverters.

Step 6 - Connecting the APsystems Optimizer to inverter

When verification is correct, connect the optimizer to the inverter. Pay

attention to polarity.

Содержание OPT700

Страница 1: ...Installation User Manual Rev 1 1 ALTENERGY POWER SYSTEM Inc www APsystems com All Rights Reserved OPT700 OPT700L DC Optimizer...

Страница 2: ...tems 7 Required parts and tools to complete the installation 7 Installation Procedures 8 Step 1 Attaching the APsystems Optimizer to the Racking or the PV Module Frame 8 Step 2 Connecting the APsystem...

Страница 3: ...icates information that is important for Optimizer operation Follow these instructions closely Safety Instructions Do NOT disconnect the PV module from the APsystems optimizer without first disconnect...

Страница 4: ...rantee that interference will not occur in a particular installation If this equipment causes harmful interference to radio or television reception the following measures might resolve the issues A Re...

Страница 5: ...ty Instructions Symbols replace words on the equipment on a display or in manuals Trademark Caution risk of electric shock Equipment protected throughout by double insulation or reinforced insulation...

Страница 6: ...e energy harvested from each module It can achieve module level Maximum Power Point Tracking MPPT and plays a critical part in the whole power system The APsystems PV Power Optimizer system is compris...

Страница 7: ...derperforms compared with the other units the APsystems optimizer ensures top performance from the array by maximizing the performance of each module The APsystems Optimizer system is reliable safe an...

Страница 8: ...stallation of this equipment includes the risk of electric shock WARNING Do not touch any live parts in the system including the PV array when the system has been connected to the electrical grid WARN...

Страница 9: ...ching to the PV Module Frame Figure 3 Step 2 Connecting the APsystems Optimizer to the PV Module Figure 4 WARNING Connect the PV module to the optimizer INPUT1 interface when the optimizer connects wi...

Страница 10: ...s designed to accomodate labels in vertical or horizontal orientation to meet all the field PV connections a Each APsystems optimizer has removable serial number labels Peel the labels off affix one t...

Страница 11: ...ess of the APsystems optimizer connection can be verified by measuring the polarity and magnitude of the total string output voltage For example each APsystems optimizer connect to two PV modules and...

Страница 12: ...r Connect all the PV modules to their optimizers securely There is something wrong with PV Power Optimizer Please return the optimizer to your distributor for replacement or contact APsystems Customer...

Страница 13: ...ect the PV module DC wire connectors from the optimizer and disconnect the optimizer output cables 4 Remove the optimizer from the PV array racking B Install a replacement optimizer to the rack and co...

Страница 14: ...mm x 26 4mm Weight 1 1lbs 0 5kg Enclosure Rating IP67 NEMA 6P Protection Class II Overvoltage Category II Operational environment Outdoor Use Pollution Degree Classification PD3 Wet Locations Classifi...

Страница 15: ...B403 No 188 Zhangyang Road Pudong Shanghai Tel 86 021 3392 8205 Mail info altenergy power com APsystems Australia Suite 502 8 Help Street Chatswood NSW 2067 Australia Tel 61 0 2 8034 6587 Mail info al...

Страница 16: ...Each APsystems optimizer has a removable serial number label located on the mounting plate Peel the label and affix it to the respective location on the APsystems installation map Installation Map Te...

Отзывы: