3-1
Preventive Maintenance
Routine Maintenance
129367-410
Table 3–1. Periodic Maintenance Schedule for Century Sterilizer
SERVICE REQUIRED
BI-MONTHLY INSPECTION
1
2
3
4
5
6
1.0 PREPARATIONS FOR PERIODIC MAINTENANCE
1.1 Discuss equipment operation with department personnel.
X
X
X
X
X
X
1.2 Inspect printouts for signs of trouble.
X
X
X
X
X
X
1.3 Install test equipment.
X
X
X
X
X
X
1.4 When necessary, shut off all building services (using lockout and tag
out procedures), and drain all utility lines.
X
X
X
X
X
X
2.0 DOOR ASSEMBLY
2.1 Verify door up proximity switch setting.
X
X
X
X
X
X
2.2 Check tension on power door cable.
X
X
X
X
X
X
2.3 Check door for smooth operation.
X
X
X
X
X
X
3.0 STEAM AND WATER SUPPLY HAND VALVE
3.1 Inspect each hand valve for smooth operation and proper valve seating.
X
X
X
X
X
X
3.2 Inspect valve for leaks.
X
X
X
X
X
X
Maintenance procedures described in Sections 3 and 4 should be performed
regularly at the intervals indicated, using the maintenance schedule in
Table 3-1
as a guide. Local conditions (water quality, usage, etc.) may require
more frequent maintenance than indicated. Refer to
ILLUSTRATED PARTS
BREAKDOWN
publication (P129367-409) for replacement parts list.
If an operating problem occurs, refer to Section 5,
Troubleshooting.
PREVENTIVE MAINTENANCE
3
WARNING - PERSONAL
INJURY AND/OR EQUIP-
MENT DAMAGE HAZARD:
Safe and reliable opera-
tion of this equipment re-
quires regularly sched-
uled preventive mainte-
nance in addition to the
faithful performance of
routine maintenance. Con-
tact STERIS to schedule
preventive maintenance.
3.1 Periodic
Maintenance
Schedule